Every grid connection point in Great Britain
One page per site in NESO's register of 26 November 2026: who is queuing, for how much, until when, and which dates have moved.
1,035connection points
1,674projects
591 GWwaiting to connect
82 GWconnected
Most date moves
- Alverdiscott 400kV: 10,308 MW waiting, 7 date moves
- Grimsby West 400kV: 6,555 MW waiting, 5 date moves
- High Marnham 400kV: 3,596 MW waiting, 5 date moves
- Cilfynydd 400kV: 2,998 MW waiting, 4 date moves
- Leeds North Connection Node C 400kV: 2,430 MW waiting, 4 date moves
- Enderby 400kV: 2,082 MW waiting, 4 date moves
- Kingsnorth 400kV: 2,850 MW waiting, 3 date moves
- North Anglia Connection Node E 400kV: 2,390 MW waiting, 3 date moves
- Wymondley 400kV: 1,492 MW waiting, 3 date moves
- Cellarhead 400kV: 1,400 MW waiting, 3 date moves
- Fiddlers Ferry 275kV: 1,300 MW waiting, 3 date moves
- Kincardine North 400kV: 1,249 MW waiting, 3 date moves
- Warley 275kV: 1,231 MW waiting, 3 date moves
- NORTH ANGLIA CONNECTION NODE A 400kV SUBSTATION: 400 MW waiting, 3 date moves
- Berryburn 275/33kV GSP: 160 MW waiting, 3 date moves
Biggest queues
- Alverdiscott 400kV: 10,308 MW waiting, 7 date moves
- Creyke Beck 400kV: 7,578 MW waiting
- Grimsby West 400kV: 6,555 MW waiting, 5 date moves
- Trent Valley South Connection Node D 400kV: 6,420 MW waiting
- Longside 400kV: 5,500 MW waiting, 2 date moves
- Necton 400kV: 5,188 MW waiting, 2 date moves
- Cheshire Connection Node A 400kV: 5,130 MW waiting
- South Anglia Connection Node C 400kV: 4,874 MW waiting
- Trent Valley South Connection Node B 400kV: 4,870 MW waiting
- Trent Valley South Connection Node C 400kV: 4,589 MW waiting
- Norwich Main 400kV: 4,484 MW waiting
- Navenby 400kV: 4,370 MW waiting, 1 date moves
- Birkhill Wood 400kV: 4,350 MW waiting
- Drax 400kV: 4,306 MW waiting
- East Claydon 400kV: 4,125 MW waiting, 1 date moves
National Grid Electricity Transmission (England and Wales) (482)
- 132kV bay at Iron Acton
- APPLEFORD 400kV SUBSTATION
- Aberthaw 275kV
- Aberthaw B 275/132kV
- Abham 132kV
- Alverdiscott 400kV
- Amersham Main 132kV
- Amersham Main 400kV
- Appleford 400kV
- Axminster 132kV
- Axminster 400kV
- Barking West
- Basingstoke East 400kV
- Berkswell
- Berkswell 275kV
- Berkswell B 275kV
- Bicker Fen
- Bicker Fen 400kV
- Biggleswade 400kV
- Birkhill Wood 400kV
- Bishops Wood
- Bishops Wood 132kV
- Blyth 275kV
- Blyth 400kV
- Bodelwyddan 400kV
- Bolney
- Bolney 132kV
- Bolney 400kV
- Borders Connection Node A 400kV
- Borders Connection Node A 400kV
- Botley 400kV
- Botley West 400kV
- Bradford West 275kV
- Braintree 400kV
- Bramford 400kV
- Bramford B 400kV
- Bramley
- Bramley 400kV
- Braybrooke 400kV
- Bridgewater 400kV
- Bridgwater 400/132kV
- Brinsworth 400kV
- Brinsworth B 400kV
- Bulls Lodge 400kV
- Burwell 132kV
- Burwell 400kV
- Burwell Main 400kV
- Burwell South 400kV
- Bushbury 275kV
- Butlers Wood 400kV
- CELTIC SEA 275/66KV OFFSHORE SUBSTATION
- Canterbury North 400kV
- Capenhurst
- Capenhurst 275kV
- Capenhurst 400kV
- Carrington 275kV
- Carrington 400KV
- Cellarhead 132kV
- Cellarhead 400kV
- Cheshire Connection Node A 400kV
- Cheshire Connection Node A2 400kV
- Cheshire Connection Node B 400kV
- Chessington 132kV
- Chesterfield 400kV Substation (Not yet constructed)
- Chickerell 400kV
- Chickerell B 400kV
- Chickerell-Mannington 400kV
- Chiltern Connection Node A 400kV
- Chiltern Connection Node B 400kV
- Chiltern Connection Node C 132kV
- Chiltern Connection Node C 400kV
- Chiltern Connection Node D 400kV
- Chirk
- Chirk 132kV
- Cilfynydd 400kV
- Coddington 400kV
- Connah's Quay 400kV
- Coryton South 400kV
- Cottam 400kV
- Cottered 400kV
- Cousland 400kV
- Cowley 400kV
- Creyke Beck
- Creyke Beck 132kV
- Creyke Beck 400kV
- Culham Jet 400kV
- DERBYSHIRE CONNECTION NODE E 132 KV SUBSTATION
- DERBYSHIRE CONNECTION NODE E 132KV SUBSTATION
- DEWLEY HILL EHV
- DIDCOT 400/132KV SUBSTATION
- DRAGON GREEN 400kV SUBSTATION
- Daines 400kV
- Derbyshire Connection Node A 400kV
- Derbyshire Connection Node B 400kV
- Derbyshire Connection Node C 400kV
- Derbyshire Connection Node D 400kV
- Derbyshire Connection Node E 400kV
- Derbyshire Connection Node F 132KV
- Derbyshire Connection Node G 400kV
- Derbyshire Connection Node H 400kV
- Derbyshire Connection Node I 400kV
- Didcot 132kV
- Didcot 132kV GIS
- Didcot 400kV
- Drakelow
- Drakelow 132kV
- Drakelow 400kV
- Drax 132kV
- Drax 400kV
- Dumfries North 400/132kV substation
- Dungeness 400kV
- Dunstable 400kV
- EA2A and EA2B 275/66kV Offshore Platform
- EAST KENT CONNECTION NODE B 132KV SUBSTATION
- ELSTREE B 275KV SUBSTATION
- EQUINOR 66KV OFFSHORE SUBSTATION
- ERBYSHIRE CONNECTION NODE E 132kV SUBSTATION
- Earl Shilton 275kV
- Earl Shilton 400kV
- East Anglia Connection Node E 400kV
- East Anglia Project Three Offshore Platform
- East Claydon 400kV
- East Claydon GSP (NGED EM)
- East Kent Connection Node B 400kV
- East Kent connection node A 400kV
- Eaton Socon 400kV
- Eggborough 400kV
- Elland 132kV
- Elmya Grange 400kV
- Elton (Merseyside 132kV Substation)
- Enderby 400kV
- Exeter 400kV
- Exeter Main 400kV
- Farmoor 400kV
- Fawley
- Fawley 132kV
- Feckenham 400kV
- Ferrybridge B 132kV
- Ferrybridge C 275kV
- Fiddlers Ferry 275kV
- Five Estuaries 220/66 kV Offshore
- Fleet 400kV
- Folly Farm 132kV
- Friston 400kV
- Frodsham 132kV
- Frodsham 400kV
- Future Swansea North 132kV
- GALLOS 66KV OFFSHORE SUBSTATION
- Gorstage 400kV
- Grain West 400kV
- Gravity 400kV
- Grendon 132kV
- Grendon 400kV
- Greystones A 275kV
- Greystones B 275kV
- Grimsby West
- Grimsby West 132kV
- Grimsby West 400kV
- Gwyddelwern 400kV
- Hadleigh 400kV
- Hams Hall 400kV
- Harker
- Harker 132kV
- Harker 400/132KV
- Harker 400kV
- Harlaston 400kV
- Hartmoor
- Hartmoor 275kV
- Hawthorn Pit
- Hawthorn Pit 400kV
- Hedon 275kV
- High Marnham 400kV
- Hirwaun
- Hope 400kV
- Humber Refinery 400kV
- Hurst 275kV
- Hutton 400kV
- IMW01 OFFSHORE 275/66KV OFFSHORE SUBSTATION
- Imperial Park 400kV
- Imperial Park B 400kV
- Indian Queens 400kV
- Iron Acton 132kV
- Iron Acton 275kV
- Ironbridge 400kV
- Iver 275kV
- Jersey Farm 400kV
- Jubilee Farm 275kV
- KINGSNORTH B 400KV SUBSTATION
- Keadby 400kV
- Kearsley 275kV
- Kegworth B (Derbyshire Connection Node C) 132kV
- Kellingley 400kV
- Kellingley IDNO
- Kemsley
- Kemsley 400kV
- Killingholme 400kV
- Kingsnorth 132kV
- Kingsnorth 400kV
- Kirkby 275/33kV
- Kirkby 275kV
- LAVENDON 400KV SUBSTATION
- LLYWELYN EXTENSION OFFSHORE WIND FARM 66/275KV OFFSHORE SUBSTATION
- Lackenby 400kV
- Laleham 132kV
- Laleham GSP (SEPD)
- Lancashire Connection Node B 400kV
- Landulph 400kV
- Langage 400kV
- Lapwing Fen II (Walpole) IDNO
- Leeds North Connection Node A 400kV
- Leeds North Connection Node B 400kV
- Leeds North Connection Node C 132kV
- Leeds North Connection Node C 400kV
- Leeds North Connection Node D 400kV
- Leeds North Connection Node E 132KV
- Leeds North Connection Node E 275kV
- Leeds North Connection Node G
- Leeds South Connection Node B 132kV
- Leeds South Connection Node C 400kV
- Legacy 400kV
- Letchmore Heath 132kV
- Lincolnshire Coastal Node 400kV
- Lincolnshire Coastal Node B 400kV
- Lister Drive 275kV
- Little Horsted
- Littlebrook 132kV
- Littlebrook 400kV
- Llandyfaelog 132kV
- Llandyfaelog 400/132kV
- Llanteg 400kV
- London North East Connection Node A
- London North East Connection Node A 132kv
- London North East Connection Node A 400kV
- London North West Connection Node A 132kV
- London North West Connection Node A 400kV
- London North West Connection Node B 400kV
- London South Connection Node A 132kV
- London West Connection Node A 400kV
- London West Connection Node B 400kV
- Long Stratton 400kV
- Lovedean 400kV
- MERERID OFFSHORE WIND FARM 220/32KV SUBSTATION
- MERSEYSIDE CONNECTION NODE A 400KV SUBSTATION
- MID WALES CONNECTION NODE A 400KV SUBSTATION
- Mablethorpe 400kV
- Manchester South Connection Node B 400kV
- Manchester South connection node A 400kv
- Mannington 400kV
- Marchwood 400kV
- Margam 275kV
- Margam B 400kV
- Market Harborough 400kV
- Marston Vale 400kV
- Melksham 400kV
- Melksham B 132KV
- Melksham B 400kV
- Mid Wales Connection Node A
- Mid Wales West 132kV
- Middleton 400KV
- Mill Hill 275kV
- Minety 400kV
- Monk Fryston 275kV
- Monk Fryston 400kV
- NORTH ANGLIA CONNECTION NODE A 400kV SUBSTATION
- NORTH KENT CONNECTION NODE C 132KV SUBSTATION
- Nant Y Maen 132KV
- Navenby 132kV
- Navenby 400kV
- Necton 400kV
- Newchurch 400kV
- Ninfield
- Ninfield 400kV
- North Anglia Connection Node A 132kV
- North Anglia Connection Node A 400kV
- North Anglia Connection Node B 400kV
- North Anglia Connection Node C 400kV
- North Anglia Connection Node D 132kV
- North Anglia Connection Node E 400kV
- North Falls Offshore Platform
- North Humber Connection Node A 400kV
- North Humber Connection Node B 132kV
- North Humber Connection Node C 132kV
- North Humber Connection Node C 400kV
- North Humber Connection Node E 400kV
- North Kent Connection Node A 400kV
- North Kent Connection Node B 132kV
- North Kent Connection Node C 400kV
- North Wales connection Node A 400kV
- NorthFleet 400kV
- Northfleet East 400kV
- Norton
- Norton 275kV
- Norton 400kV
- Norton East 400kV
- Norwich Main 132kV
- Norwich Main 400kV
- Norwich Main 400kW
- Nursling 400kV
- Oakley 400kV
- Ocker Hill 275kV
- Ocker Hill C 132kV
- Oldbury 275kV
- Osbaldwick (North Humber Connection Node E) 132kv
- Osbaldwick 400kV
- Overton 275kV
- PELHAM 2 400KV SUBSTATION
- Patford Bridge 400kV
- Pelham 400kV
- Pembroke 132kV
- Pembroke 400kV
- Penn 132kV
- Penn 275kV
- Penrhos
- Pentir 400kV
- Penwortham 400kV
- Pitsmoor
- Pont Abraham
- Pont Abraham 132KV
- Pyworthy 400kV
- RWE CELTIC OFFSHORE SUBSTATION
- Rainhill
- Rassau
- Rassau 400kV
- Ratcliffe
- Ratcliffe-On-Soar 132kV
- Ratcliffe-On-Soar 400kV
- Raventhorpe 400kV
- Rayleigh 400kV
- Rayleigh Main
- Rayleigh Main 132kV
- Rayleigh Main 400kV
- Rhigos 400kV
- Rhigos B 400kV
- Richborough
- Richborough 400kV
- Rochdale
- Rochdale 275kV
- Rowdown 400kV
- Rugeley
- Rugeley 400kV
- Ryhall 400kV
- SANDFORD B 400kV SUBSTATION
- SEABANK 400/33kV SUBSTATION
- SOUTH HUMBER CONNECTION NODE A 132kV
- SOUTH WALES WEST CONNECTION NODE A 132KV
- SPR CS1 275/66KV OFFSHORE SUBSTATION
- Saltend North
- Saltholme 275kV
- Seabank
- Sealand 400kV
- Sellindge 400kV
- Severn Connection Node A 132kV
- Severn Connection Node A 400kv
- Severn Connection Node B 400kV
- Shaftesbury 132kV
- Shrewsbury 400/33kV
- Shrewsbury 400kV
- Shurton 400kV
- Sizewell 400kV
- Slough East 132kV
- Solent Connection Node A 132kV
- Solent Connection Node B 132kV
- Solent Connection Node C 400kV
- South Anglia Connection Node A 400kV
- South Anglia Connection Node B 400kV
- South Anglia Connection Node C 400kV
- South Anglia Connection Node D 132kV
- South Anglia Connection Node D 400kV
- South Anglia Connection Node E 400kV
- South Humber Bank 400kV
- South Humber Connection Node A
- South Humber Connection Node A 400kV
- South Wales East Connection Node A 275kV
- South Wales East Connection Node B 400kV
- South Wales East Node A 275kV
- South Wales West Connection Node A 400kV
- South Wales West Connection Node B 400kV
- South Wales West Connection Node C 400kV
- Southery 400kV
- Spalding North 400kV
- Spennymoor 400kV
- Staffordshire Connection Node A 400kV
- Staffordshire Connection Node B 132kV
- Staffordshire Connection Node C 400Kv
- Staffordshire Connection Node D 132kV
- Stalybridge 275kV
- Staythorpe 400kV
- Staythorpe 400kv
- Stella South
- Stella West 400kV
- Stocksbridge 400kV
- Stoke Bardolph
- Stoke Bardolph 400kV
- Sundon 400kV
- Sussex and Romney Connection Node A 400kV
- Sussex and Romney Connection Node B 132kV
- Sussex and Romney Connection Node B 400kV
- Swaffham 400KV
- Swansea North 400kV
- Taunton 400kV
- Teeside Connection Node 2 C 132/400kV
- Teeside Connection Node A 132kV
- Teeside Connection Node A 400kV
- Teeside Connection Node B
- Thetford 400kV
- Thormanby 400kV
- Thornton 400kV
- Thornton B 400kV
- Thorpe Marsh
- Thorpe Marsh 400kV
- Thurcroft 275kV
- Tideford 400kV
- Tod Point 275kV
- Torridge Offshore
- Trawsfynydd 275kV
- Trent Valley North Connection Node B 132kV
- Trent Valley North Connection Node B 400kV
- Trent Valley North Connection Node F 400kV
- Trent Valley South Connection Node A 400k
- Trent Valley South Connection Node A 400kV
- Trent Valley South Connection Node B 400kV
- Trent Valley South Connection Node C 400kV
- Trent Valley South Connection Node D 400kV
- Trent Valley South Connection Node G 400kV
- Tween Bridge 400kV
- Tynemouth 275kV
- Tynemouth GSP (NPG)
- Upper Boat 275kV
- Uskmouth 132kV
- Uskmouth 275kV
- WEST ANGLIA CONNECTION NODE B 400KV SUBSTATION
- Wakeleys 400kV
- Walham 400kV
- Walpole 132kV
- Walpole 400kV
- Walpole 400kV substations
- Waltham Cross 400kV
- Waltham Cross B 400kV
- Warley 132kV
- Warley 275kV
- Warwickshire Connection Node A 400kV
- Warwickshire Connection Node B 132kV
- Warwickshire Connection Node D 132kV
- Warwickshire Connection Node F 132kV
- Warwickshire Connection Node F 400kV
- Wearside Connection Node A 275kV
- Wearside Connection Node B 2 400kV
- Wearside Connection Node B 400kV
- Wearside Connection Node B2 400kV substation
- Wearside Connection Node C 400kV
- Wearside Connection Node D 400kV
- West Anglia Connection Node A 400kV
- West Anglia Connection Node C 400kV
- West Anglia Connection Node D 400kV
- West Anglia Connection Node E 400kV
- West Anglia Connection Node F 400kV
- West Anglia Connection Node G 400kV
- West Anglia Connection Node H 400kVSubstation
- West Anglia Connection Node I 400kV substation
- West Burton 132kV
- West Burton 400kV
- West Country Connection Node A 400kV
- West Country Connection Node C 400kV
- West Country Connection Node D 400kV
- West Country Connection Node E 400kV
- West Haddon 400kV
- West London Connection Node B 132kV substation
- West Melton
- West Weybridge 275kV
- Western Marsh 400kV
- Weston Marsh 400kV
- Whitson 275kV
- Willington 400kV
- Willington East 400kV
- Woolavington 400kV
- Wylfa 132kV
- Wylfa 400kV
- Wylfa South 400kV
- Wymondley 2 400kV
- Wymondley 400/33kV
- Wymondley 400kV
- Yaxley 400kV
SP Transmission (southern Scotland) (289)
- AGS CALDERSIDE 275KV SUBSTATION
- AGS Harestonhill BESS 400kV
- AYR DBB 275KV SUBSTATION
- Airds Hill WindFarm 132kV
- Andrew BESS 132kV
- Appin Wind Farm 132kV
- Arecleoch 132/33kV
- Armadale 132kV
- Arresgill 132kV
- Artfield Forest Wind Farm 132kV
- Auchentiber Farm BESS 400kV
- Auldhouse 400kV
- Ayr
- Ayr 275/33kV
- Ayr 275/33kV
- Ayr Farm Collector
- Ayrshire Grid 400kV
- BENDLE FARM 2.0 132KV SUBSTATION
- BISHOPS DAL ENERGY PARK 132kV SUBSTATION
- BLAIR HILL WIND FARM 132KV SUBSTATION
- BORDERS SOLAR 132/33KV SUBSTATION
- Bainsford 132/33kV
- Bankend Rig III 132kV Collector
- Bankhead 400kV
- Bargatton Farm BESS 132kV
- Benbrack Wind Farm 132/33kV
- Bendle Farm 132kV
- Bendsmoor BESS 400Kv
- Berwick 132/33kV
- Bishopbriggs BESS 400/275kV
- Blackbraes IDNO
- Blacklaw 132/33kV
- Bloch Energy Park 132kV
- Bodinglee Wind Farm 132kV
- Bonnybridge 132/33kV
- Borders Windfarm 132kV
- Bowsheils 132kV
- Boydston 400kV substation
- Braehead Park 132/33kV
- Braeside IDNO 132/33kV substation
- Braidfield Battery Storage 132kV
- Branxton 400/132kV
- Branxton 400kV
- Braxbess 400/132kV Collector
- Busby 275kV
- CHALMERSTON WINDFARM 132kV SUBSTATION
- CRAIGHEAD WIND FARM 132kV SUBSTATION
- Callisterhall 132kV
- Caple Rig 132kV
- Carntyne (SPD)
- Carrick Wind Farm
- Castlemilk 400kV
- Chapelcross 132/33kV
- Chirmorie Wind Farm substation
- Clauchrie 132/33KV
- Cloich 132kV
- Clydesmill
- Clydesmill 275/33kV
- Coalburn 132kV
- Coalburn 400kV GIS
- Coalburn North 400kV
- Coatbridge
- Cockenzie 275/33kV
- Cockenzie 275kV substation
- Cockenzie 400/275kV
- Conland
- Coylton 275/132kV
- Coylton 275kV substation
- Craig Moss Farm 132kV
- Craigdarroch Hybrid Wind & BESS 132kV
- Craigneuk 250MW BESS 275kV
- Cruachan 275kV
- Currie 275/132kV
- DALMARNOCK 132/33KV SUBSTATION
- DEVOL MOOR 132/33KV GRID SUPPLY POINT SUBSTATION
- Daer Wind Farm 132/33kV
- Dalkeith 400kV
- Dalmarnock Storage BESS 132kV
- Denny North
- Denny North 275/132kV
- Dersalloch 132/33kV
- Devilla Battery Storage 275kV substation
- Devol Moor 400/132kV
- Devonside 132/33kV
- Devonside 132kV
- Divot Hill 132/33 kV
- Drinkstone Hybrid 132/33kV substation
- Drumchapel 275/33kV
- Dumfries 132/33kV
- Dumfries North 400kV
- Dun Hill 132/33kV
- Dunbar 132/33kV
- Dunfermline 132/33kV
- Dunlaw Extension 132/33kV
- ECOKILWINNING 132KV SUBSTATION
- ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION
- East Kilbride 275/33kV
- East Kilbride 275kV
- East Kilbride B 275/33kV
- Easterhouse 275kV
- Eccles
- Eccles 400/132kV
- Eccles 400kV
- Ecomossmorran 400kV
- Elderslie 132/33kV
- Elvanfoot 275/132/33kV
- Elvanfoot 400/275/33kV
- Elvanfoot substation
- Enoch Hill 2 Wind Farm 33kV
- Er Bbr Energy 132kV
- Er Msm Energy 132kV
- Euchanhead 132kV
- FIELD GLENNISTON BESS 132KV SUBSTATION
- FIFE 2 BESS 132KV SUBSTATION
- FORSA ENERGY DENNY BESS 132KV GRID SUPPLY POINT SUBSTATION
- Fallago 400/33kV
- Fife Energy Centre 132kV substation
- Fife Grid Services Facility 275kV
- Finnieston
- GALA NORTH 132KV SUBSTATION
- GARTCLASH COLLECTOR 275KV SUBSTATION
- GH DEVCO KINCARDINE BESS 132kV SUBSTATION
- GLENTAGGART 150MW BESS 132kV SUBSTATION
- Gala North 400/132kV
- Galashiels 132/33kV
- Galileo 16 132kV
- Garscadden Park 275kV
- Giffnock 275/33kV
- Giffordland 400/132kV
- Glenglass 132/33kV
- Glenmuckloch 132/33kV
- Glenmuckloch 132kV
- Glenmuir Windfarm 132kV
- Glennifer Road BESS 132kV substation
- Glenrothes 275/33kV
- Glentaggart WF 33kV
- Glenvernoch 132kV
- Govan 132/33kV
- Greenburn Mixed Technology 132kV
- Greenock Road 275kV
- Gresham House Dalmarnock Bess 132kv
- Gresham House Gretna 400/132kv
- Gresham House Kincardine BESS 275/132kV substation
- HIGH BARDRAIN WOOD & MOOR 132KV SUBSTATION
- HIGH MATHERNOCK 132KV SUBSTATION
- Haggs Road
- Hagshaw Repowering Phase 3 132kV
- Halbeath 132kV
- Harburn 132/33kV Grid Supply Point
- Harburn 400kV
- Hare Craig 33kV
- Hare Hill Repowering 132/33kV
- Harestanes West Wind Farm 132/33kV
- Hawick
- Hawick 132kV
- Hawkwood Windfarm 33kV
- Heathland 132/33kV
- Helensburgh 132/33kV
- Holm Hill 132kV
- Hopsrig Collector
- Hopsrig Collector 132/33kV
- Hunterston 400/132kV
- Hunterston East 400kV
- Hunterston East 400kV substation
- Inverkeithing
- Inverkeithing 132/33kV
- Jonhstone 132/33kV
- KXP Alpha 3 Ayr BESS 275kV
- Kaimes
- Kelloe Mains 400kV
- Killermont
- Killoch BESS 132kV
- Kilmarnock South 400kV
- Kilmarnock Town 275/33kV
- Kilwinning 132/33kV
- Kincardine North 400kV
- Kinkell IDNO
- Kirkcaldy BESS 132kV
- Knockcronal Wind Farm 33kV
- Knockodhar Wind Farm 132kV
- L48 BESS GLEN APP 275/132KV SUBSTATION
- LADYBURN 132/33KV GRID SUPPLY POINT SUBSTATION
- LAND AT LEITHOLM 132KV SUBSTATION
- LESSNESSOCK ENERGY PARK 132KV SUBSTATION
- LOCH GELLY COLLECTOR 132KV SUBSTATION
- LONGCROFT ENERGY PARK 132KV SUBSTATION
- Ladyburn 132kV
- Lairdmannoch Energy Park 132kV substation
- Langbank 132kV
- Learlielaw Energy Storage 132kV
- Leslie 200MW BESS 275kV
- Letham 400/275kV substation
- Lethans Collector
- Lethans Collector 132kV
- Lightsource Mount Annan 132kV
- Linnmill
- Linwood 400kV
- Lorg Extension Wind Farm 132/33kV
- Lorg Wind Farm 132/32kV
- M74 West Wind Farm 132kV
- MIDDLETON FARM 400KV SUBSTATION
- Machair 275/66kV Offshore
- Manquhill Wind Farm 132/33kV
- Margree 132/33kV Collector
- Maybole
- Maybole 132/33kV
- Meadowmill 400/132kV
- Mid Hill 132kV
- Mid Moile Wind Farm 275/132kV Substatio
- Milligansbush Battery Storage 132kV
- Minnygryle Burn Energy Park 132kV substation
- Moffat 400kV
- Mossmorran Storage BESS 132KV
- Muckraw IDNO
- NLEI Windfarm 132/33kV substation
- Narie 400/132kV
- NatPower Green Energy Park 400kV
- NatPower Harburn Green Energy Park 400kV
- Near Branxton 400kV
- Neilston 400kV
- New Cumnock 275/132kV
- New Cumnock A 132kV
- New Cumnock North 132kV
- Newarthill 275 kV
- Newarthill Energy Park 275kV
- Newlands Hill 132/33kV
- Newton Stewart
- North Lanrigg
- OCHILL BESS 132KV SUBSTATION
- Olivers Forest Wind Farm 132kV
- Overhill 132kV
- Paisley
- Partrick
- Peat Law Renewable Energy Park 132kV
- Philipaugh
- Pond Flexible Energy Park 132kV
- Quantans Hill 132kV
- REDSHAW 132kV B BOARD SUBSTATION
- ROWANCRAIG WIND FARM 33KV SUBSTATION
- Red Moss Farm 132kV
- Redshaw 132kV Substation.
- Redshaw 400kV
- Redshaw Energy Park 132kV substation
- Rivox 132/33kV
- Roger Hill Farm 132kV substation
- SHAWFAIR 400KV SUBSTATION
- SPT Margree collector substation
- Saltcoats 132/33kV
- Sandyknowe 132/33kV
- Sanquhar II Wind Farm
- Scaw Law 132kV substation
- Sclenteuch Energy Park 132kV
- Scoop Hill Wind Farm 132kV
- Seat Hill 132kV
- Shepards Rig 132/33kV
- Smeaton 400/275kV
- Smeaton 400kV
- South Kyle 2 132/33kV
- Spirebush 132kV
- Stirling 132/33kV
- Stranoch Wind 132/33kV
- Strathaven 400/275kV
- Strathaven 400kV
- Strathaven GSP 33kV
- Strathleven
- Sundhope 132kV
- TH Renfrwshire 275kV
- TINNISBURN WIND FARM 132KV SUBSTATION
- Teviot 400/132kV
- Thorntonloch 400kV
- Tongland 132/11kV
- Torfichen Energy Park 132kV
- Torness 400/132kV
- Vale of Leven 132kV substation
- WESTFIELD 400/275KV
- Watchman 132kV
- West Andershaw 132kV
- Westfield 400kV
- Wether Hill 132/33KV
- Whitburn 400kV substation
- Whitehill Bess 275/132kV
- Whitelaw Brae 'A' and 'B' 33kV Substations
- Whitelaw Brae BESS 33kV substation
- Whitelee 275/33kV
- Whitelee Extension 275/33kV
- Whiteminhill 275/33kV
- Windyhill 132kV
- Windyhill 275/132kV
- Wyseby Hill Energy Farm 400kV
SSEN Transmission (northern Scotland) (264)
- 17 ACRES BESS 275KV SUBSTATION
- ACHANY EXTENSION WIND FARM 132/33KV
- ALCEMI SCORE BATTERY ENERGY STORAGE FACILITY 400KV SUBSTATION
- ALYTH BESS STATION 400KV SUBSTATION
- Aberarder Extension Wind Farm 132/33kV
- Aberarder Wind Farm 132/33kV
- Abernethy 2
- Abhainn Dubh Wind Farm 132kV
- Acheilidh Wind farm 132kV
- Achrugan 132kV
- Alcemi Score Battery 400kV
- Alness
- Alness 2 275/33 kV GSP
- Alyth 400kV
- Alyth Solar and Battery 400/132kV
- An Suidhe 275/33kV
- Arbroath
- Arbroath 2 132/33kV GSP
- Arnish 275kV
- Arnish Lewis Hub 400kV
- Aultmore Wind Farm 132/33kV
- BALLYGROGGAN 132/33KV SUBSTATION
- BEAULY 02 BESS 132kV SUBSTATION
- BEINN THURSUNN REPOWER 275/33KV
- BRORA 132/33KV GRID SUPPLY POINT SUBSTATION
- Baillie 275KV
- Balinoe 132kV substation
- Balliemeanoch 275kV
- Balnespick Wind Farm 132kV/33kV
- Banniskirk 400kV
- Beauly 132/33 kV GSP
- Beauly substation 275KV
- Beaw Field 132/33kV
- Beinn an Tuirc
- Beinneun Windfarm 2
- Berryburn 275/33kV GSP
- Bhlaraidh 132/33kV
- Blackhillock 275kV
- Blackhillock 400kV
- Blackhillock substation
- Blarghour
- Braco West
- Braegrundie Farm 132kV
- Breackerie 132kV
- Breakish 132kV
- Brechin 400/275 kV
- Bridge of Dun
- Broadford
- Broadford 132kV
- Brora
- CAITHNESS ENERGY STORAGE 400KV SUBSTATION
- CARRADALE 3 132/33KV GRID SUPPLY POINT SUBSTATION
- CRAIG WATCH WIND FARM 132KV SUBSTATION
- Cairnford
- Caorach 132 KV
- Car Duibh 275kV
- Carn Fearna Wind Farm 132/33kV
- Carradale 1
- Carradale 2 132/33kV GSP
- Cassley
- Ceislien Wind Farm
- Charleston GSP 132/33kV
- Chleansaid Wind Farm 132kV
- Clachan 2 132/33kV GSP
- Clash Gour Wind Farm 132kV
- Clashindarroch Windfarm Extension 132kV
- Cloiche 132/33kV
- Clune 132/33 kV
- Cnoc Buidhe 132kV/33kV
- Coachford 400kV
- Coille Linne 132kV
- Coire Glas
- Connagill 132kV
- Connagill 275kV
- Correen Hills Wind Farm 132kV
- Corriegarth 132/33kV substation
- Corriemoillie 132/33kV
- Corriemoillie 132kV
- Corriemoillie 2 400/132kV
- Cott's Farm 132kV
- Coupar Angus 132/33kV
- Coupar Angus 2
- Craig Murrail
- Craig Murrail 275/33kV GSP
- Craig Murrail 275kV
- Creachan Wind Farm 132/33kV
- Creag Dhubh 275/132/33kV
- Creag Dhubh Wind Farm and BESS 132kV
- Creag Riabhach 132/33kV
- DEUCHERAN HILL 2 132KV SUBSTATION
- DOUNREAY 2 275 kV SUBSTATION
- DRUM OF CLUNAS WIND 275KV SUBSTATION
- DUNACH WIND 132KV SUBSTATION
- Dalchork 132kV
- Dell 132kV
- Dorenell BESS 132KV substation
- Dorenell Extension Wind Farm 400kV
- Dounreay 2 275/33kV GSP
- Dunan Hill 400kV substation
- Dunvegan 132/33kV Grid Supply Point
- Dyce 132/33kV
- Dyce 132/33kV
- Earba PSH Powerhouse
- Earraghail 275/33KV
- Edinbane 132/33kV
- Elchies 132/33kV
- Elgin
- Energy Isles 132kV
- FARR WIND FARM 132/33KV SUBSTATION
- FIDDES 275/33KV GRID SUPPLY POINT SUBSTATION
- FORT AUGUSTUS 2 400/33kV GRID SUPPLY POINT SUBSTATION
- Fairburn Extension 132/33kV
- Fearna Pump Storage Hydro 2 400/15kV
- Fetteresso
- Fetteresso 132/33kV GSP
- Fetteresso 132kV substation
- Fiddes
- Finstown
- Finstown (Orkney)
- Fort Augustus 2 400kV
- Fort Augustus 400kV
- Fyrish 132kV
- Fyrish 275kV
- GALILEO 07 LIMITED 132KV SUBSTATION
- GALILEO 12 LIMITED 132KV SUBSTATION
- GLENTARKEN WIND FARM 132/33KV SUBSTATION
- Garlogie Production A 275/33kV
- Garlogie Production B 275/33kV
- Garlogie Production C 275/33kV
- Garvary 132kV
- Gills Bay
- Gills Bay 132kV
- Glen Earrach PSH 400kV substation
- Glen Lednock 132kV
- Glen Ullinish 132/33kV
- Glen Ullinish Extension 132/33kV
- Glendye Wind Farm
- Greens 400kV
- Grimshader Wind Farm Substation132 KV
- Grudie Bridge
- Heastabhal Wind Farm Substation 132 KV
- High Constellation 132/33kV
- Highland BESS 132kV
- Highland Wind Farm 132/33kV substation
- Hollandmey Renewable Energy Development132/33kV
- Hurlie 400kV substation
- ICHRACHAN 132/33KV GRID SUPPLY POINT SUBSTATION
- INVERNESS 132/33KV GRID SUPPLY POINT SUBSTATION
- Inveroykel Wind Farm 132kV
- Keith 1 132/33kV GSP
- Keith 132kV
- Keith 2 132/33kV GSP
- Keith Solar Farm 275kV
- Kellas Wind Farm 132kV
- Kilbraur Wind Farm
- Killin
- Killin 132/11kV
- Kinardochy Substation 400/275kV
- Kinmuck BESS 132kV
- Kintore
- Kintore 275kV
- Knocknagael 132kV
- Knockton Wind Farm 132kV
- Kynachan BESS 132kV
- L48 BESS Dams of Craigie
- LEARNEY BESS 132KV
- LGB300 400KV
- Lairg
- Lethen Wind Farm 132/33kV
- Leuchland Farm IDNO
- Limekilns 132/33kV substation
- Loch Fearna Pumped Storage 400/18kV
- Loch Kemp 275kV Switching Station
- Loch Liath 132/33kV
- Loch Luichart Extension II
- Loch Nan Eun 275/18kV
- Loch na Cathrach 275kV Switching Station
- Lochay 132/11kV
- Longmorn Energy Park 275kV
- Longside 132kV
- Longside 400kV
- Lunanhead
- Lunanhead 2
- Lyndhurst
- Lynemore Windfarm 132kV
- MacDuff 132/33kV GSP
- Melvich Community Wind Farm 132/33kV
- Milton of Craigie
- Mossy Hill 132kV
- Muaitheabhal 132/33kV
- Mybster 2 132/33kV
- Mybster 3 132/33kV
- Mybster 4 132/33kV GSP
- NATPOWER KINTORE 2 GREEN ENERGY PARK 275KV SUBSTATION
- NEW CARRADALE 132KV SUBSTATION
- NEW FETTERESSO 132KV SUBSTATION
- NEW TAYNUILT 132 KV SUBSTATION
- Nairn 132/33kV Grid Supply Point
- New Abernethy 132kV
- New Connagill 275/132kV
- New Dalchork 132kV
- New Deer 2 132kV
- New Deer 2 400kV
- New Deer 400kV
- New Dounreay 400kV substation
- New Dunoon 132/33kV GSP
- New East Coast 400kV
- New North East 275kV
- New North East Substation 400kV
- New North West 132kV
- New Spittal 275kV
- Northern Shetland 400kV
- Orrin
- Ourack 132/33kV
- Oykel Wind Farm 132kV
- PENINSULA ENERGY PARK 220kV SUBSTATION
- POLLIE HILL WIND FARM 132KV SUBSTATION
- Pentland Floating Offshore Wind Farm 132/66kV substation
- Persley 132/33kV GSP
- Peterhead 132KV
- Peterhead 2 400kV Busbar Extension
- Peterhead 275kV
- Peterhead 400kV
- Peterhead Grange
- Rannoch
- Redmoss
- Rothienorman 2 400/33kV
- Rothienorman 400/33kV
- Rothienorman 400kV
- Rowan 275/33kV
- ST FERGUS 132KV SWITCHING STATION
- Scatsta 132kV
- Sheirdrim 132kV
- Shin 1
- Slickly Wind Farm 132kV
- Spittal 132kV
- Spittal 2 400kV
- Spittal 400kV
- St Fergus
- St Fergus Mobil 132/11kV
- Stornoway
- Stracathro BESS 275kV
- Strathy South 132/33kV
- Strathy Wood 132/33kV
- Strichen
- Strichen 132/33kV GSP
- Tangy IV 132KV
- Tarland 132/33kV GSP
- Taynuilt 132/33kV GSP
- Tealing 132kV
- Tealing 400kV
- Tealing IDNO 132/33kV
- Teindland 132/33KV Wind Farm
- Thurso South
- Thurso South 275kV
- Thurso South 400kV
- Tolkien Farm 132kV
- Tomatin 132kV Substation Extension
- Tomchrasky Wind Farm 132/33kV
- West Saval Substation 132 kV
- Westfield 132/33kV
- Whitehouse 275kV
- Womblehill BESS Farm 132kV
- Woodcock Hill WF