MacDuff 132/33kV GSP: grid connection queue
MacDuff 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 50 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| YAMAL BESS | OPDE UK LIMITED | Battery storage | 50 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Macduff GSP | SSEN Distribution | 2.2 km | ||
| Macduff Primary | SSEN Distribution | 2.2 km | 0 MW | 13 MW |
| Portsoy Primary | SSEN Distribution | 11.1 km | 0 MW | 0 MW |
| Marnoch Primary | SSEN Distribution | 11.6 km | 0 MW | 1.5 MW |
| Turriff Primary | SSEN Distribution | 12.2 km | 0 MW | 0 MW |
| Cullen Primary | SSEN Distribution | 17.9 km | 0 MW | 0 MW |
Thinking of connecting near MacDuff 132/33kV GSP?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Greens 400kV: 3,500 MW waiting
- Strichen 132/33kV GSP: 67 MW waiting
- Strichen: 25 MW waiting
- New Deer 2 400kV: 1,180 MW waiting
- New Deer 400kV: 760 MW waiting