Greens 400kV: grid connection queue
Greens 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 3,500 MW are waiting to connect here (largest by capacity: offshore wind). Contracted dates run from 31 Mar 2031 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Caledonia Offshore Wind Farm | CALEDONIA OFFSHORE WIND FARM LIMITED | Offshore wind | 2,000 | 31 Mar 2031 | Medium | 31 Mar 2031 | Scoping | none |
| Stromar Offshore Windfarm | Stromar Offshore Wind Farm Limited | Offshore wind | 1,500 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Methlick Primary | SSEN Distribution | 9.8 km | 0 MW | 0 MW |
| Fyvie Primary | SSEN Distribution | 9.9 km | 0 MW | 0 MW |
| Turriff Primary | SSEN Distribution | 10.5 km | 0 MW | 0 MW |
| Maud Primary | SSEN Distribution | 10.6 km | 0 MW | 0 MW |
| New Pitsligo Primary | SSEN Distribution | 11.0 km | 0 MW | 1.1 MW |
| Rothienorman GSP | SSEN Distribution | 16.5 km |
Thinking of connecting near Greens 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- New Deer 2 400kV: 1,180 MW waiting
- New Deer 400kV: 760 MW waiting
- New Deer 2 132kV: 375 MW waiting
- Strichen 132/33kV GSP: 67 MW waiting
- Strichen: 25 MW waiting