New Deer 2 132kV: grid connection queue
New Deer 2 132kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 375 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2033 to 31 Oct 2033.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| L48 BESS Burnside | S4 UK DEV LTD | Battery storage | 200 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
| UPPER GREENFIELDS BESS | S4 UK DEV LTD | Battery storage | 175 | 31 Oct 2033 | Low | 31 Oct 2033 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 20 Oct 2026 | UPPER GREENFIELDS BESS | 31 Oct 2032 | 31 Oct 2033 | +12 months |
| 13 Oct 2026 | UPPER GREENFIELDS BESS | 31 Oct 2033 | 31 Oct 2032 | -12 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Maud Primary | SSEN Distribution | 4.0 km | 0 MW | 0 MW |
| New Pitsligo Primary | SSEN Distribution | 7.9 km | 0 MW | 1.1 MW |
| Methlick Primary | SSEN Distribution | 10.6 km | 0 MW | 0 MW |
| Strichen Primary | SSEN Distribution | 11.0 km | 0 MW | 5.7 MW |
| Strichen GSP | SSEN Distribution | 11.0 km | ||
| Mintlaw Primary | SSEN Distribution | 12.4 km | 0 MW | 0 MW |
Thinking of connecting near New Deer 2 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- New Deer 2 400kV: 1,180 MW waiting
- New Deer 400kV: 760 MW waiting
- Strichen 132/33kV GSP: 67 MW waiting
- Strichen: 25 MW waiting
- Greens 400kV: 3,500 MW waiting