Benzene

How we work out a realistic connection date

Learned from our own copies of NESO's register, 6 Dec 2024 to 17 Nov 2026.

A contracted connection date is a promise, not a forecast. So we checked how those promises have actually held up. We took every project waiting to connect in our earliest copy of the register, grouped them by technology and by how far away their contracted date was, and looked at where each one stood two years later: same date, moved later, moved earlier, or gone from the register.

For any project today, we find its group and report three things. Date risk: High if half or more of similar projects moved a month or more later, Medium from a quarter, otherwise Low. Likely date: the contracted date plus the typical move, when the risk is High; otherwise the contracted date. Dropout: the share of similar projects that left the register. Where a group is small, we use all technologies together.

The pattern is clear. Dates within two years slip far more often than dates further out, so a project's risk rises as its date gets closer.

TechnologyContracted date wasProjects still listedMoved laterTypical moveLeft the register
Battery storageunder 2 years8157%24 months8%
Battery storage2 to 5 years11232%17 months9%
Battery storage5 years or more3188%24 months8%
Offshore windunder 2 years743%31 months50%
Offshore wind2 to 5 years2232%20 months21%
Offshore wind5 years or more555%24 months18%
Onshore windunder 2 years3661%26 months19%
Onshore wind2 to 5 years10659%23 months12%
Onshore wind5 years or more11512%32 months3%
Otherunder 2 years3361%31 months34%
Other2 to 5 years3333%24 months15%
Other5 years or more498%30 months9%
Solarunder 2 years1369%45 months7%
Solar2 to 5 years633%16 months25%
Solar5 years or more2010%36 months5%
Solar + storageunder 2 years3591%24 months42%
Solar + storage2 to 5 years6932%19 months18%
Solar + storage5 years or more2697%24 months11%
Allunder 2 years20564%24 months23%
All2 to 5 years34841%20 months13%
All5 years or more8268%24 months9%

This is a statistical view from public records, not a forecast for any single project and not engineering advice. It ignores project-specific facts like works already started. A screening report reads those properly.