Strichen 132/33kV GSP: grid connection queue

Strichen 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

1 project with 67 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Jun 2024 to 30 Jun 2024.

1project in the queue
67 MWwaiting to connect
0 MWalready connected
67 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Bilbo FarmLEL BILBO SOLAR LIMITEDSolar + storage6730 Jun 2024n/aUnder Construction/Commissioning2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
27 Oct 2026Bilbo Farm31 Oct 202430 Jun 2024-4 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Maud PrimarySSEN Distribution3.2 km0 MW0 MW
New Pitsligo PrimarySSEN Distribution6.0 km0 MW1.1 MW
Strichen PrimarySSEN Distribution8.8 km0 MW5.7 MW
Strichen GSPSSEN Distribution8.8 km
Mintlaw PrimarySSEN Distribution11.3 km0 MW0 MW
Methlick PrimarySSEN Distribution12.9 km0 MW0 MW

Thinking of connecting near Strichen 132/33kV GSP?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.