Strichen 132/33kV GSP: grid connection queue
Strichen 132/33kV GSP Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
1 project with 67 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Jun 2024 to 30 Jun 2024.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Bilbo Farm | LEL BILBO SOLAR LIMITED | Solar + storage | 67 | 30 Jun 2024 | n/a | Under Construction/Commissioning | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 0 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 27 Oct 2026 | Bilbo Farm | 31 Oct 2024 | 30 Jun 2024 | -4 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Maud Primary | SSEN Distribution | 3.2 km | 0 MW | 0 MW |
| New Pitsligo Primary | SSEN Distribution | 6.0 km | 0 MW | 1.1 MW |
| Strichen Primary | SSEN Distribution | 8.8 km | 0 MW | 5.7 MW |
| Strichen GSP | SSEN Distribution | 8.8 km | ||
| Mintlaw Primary | SSEN Distribution | 11.3 km | 0 MW | 0 MW |
| Methlick Primary | SSEN Distribution | 12.9 km | 0 MW | 0 MW |
Thinking of connecting near Strichen 132/33kV GSP?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Strichen: 25 MW waiting
- New Deer 2 400kV: 1,180 MW waiting
- New Deer 400kV: 760 MW waiting
- New Deer 2 132kV: 375 MW waiting
- Greens 400kV: 3,500 MW waiting