New Deer 400kV: grid connection queue

New Deer 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026

2 projects with 760 MW are waiting to connect here (largest by capacity: offshore wind, battery storage). Contracted dates run from 31 Mar 2029 to 31 Oct 2029.

2projects in the queue
760 MWwaiting to connect
900 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Green Volt Offshore WindfarmGreen Volt Offshore Windfarm LtdOffshore wind56031 Mar 2029Medium31 Mar 2029Scopingnone
Zenobe New Deer Battery StorageZENOBE ENERGY LIMITEDBattery storage20031 Oct 2029Medium31 Oct 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Maud PrimarySSEN Distribution4.0 km0 MW0 MW
New Pitsligo PrimarySSEN Distribution7.9 km0 MW1.1 MW
Methlick PrimarySSEN Distribution10.6 km0 MW0 MW
Strichen PrimarySSEN Distribution11.0 km0 MW5.7 MW
Strichen GSPSSEN Distribution11.0 km
Mintlaw PrimarySSEN Distribution12.4 km0 MW0 MW

Thinking of connecting near New Deer 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.