New Deer 400kV: grid connection queue
New Deer 400kV Substation · SSEN Transmission (northern Scotland) · register of 26 November 2026
2 projects with 760 MW are waiting to connect here (largest by capacity: offshore wind, battery storage). Contracted dates run from 31 Mar 2029 to 31 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Green Volt Offshore Windfarm | Green Volt Offshore Windfarm Ltd | Offshore wind | 560 | 31 Mar 2029 | Medium | 31 Mar 2029 | Scoping | none |
| Zenobe New Deer Battery Storage | ZENOBE ENERGY LIMITED | Battery storage | 200 | 31 Oct 2029 | Medium | 31 Oct 2029 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Maud Primary | SSEN Distribution | 4.0 km | 0 MW | 0 MW |
| New Pitsligo Primary | SSEN Distribution | 7.9 km | 0 MW | 1.1 MW |
| Methlick Primary | SSEN Distribution | 10.6 km | 0 MW | 0 MW |
| Strichen Primary | SSEN Distribution | 11.0 km | 0 MW | 5.7 MW |
| Strichen GSP | SSEN Distribution | 11.0 km | ||
| Mintlaw Primary | SSEN Distribution | 12.4 km | 0 MW | 0 MW |
Thinking of connecting near New Deer 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- New Deer 2 400kV: 1,180 MW waiting
- New Deer 2 132kV: 375 MW waiting
- Strichen 132/33kV GSP: 67 MW waiting
- Strichen: 25 MW waiting
- Greens 400kV: 3,500 MW waiting