London North West Connection Node A 400kV: grid connection queue

London North West Connection Node A 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 1,000 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

1project in the queue
1,000 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Amersham MainAmersham 10 Renewables LimitedSolar + storage1,00031 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Kimberley Rd B 11kVUK Power Networks0.7 km38 MW8.8 MW
Amberley Rd 11kVUK Power Networks2.0 km118 MW29 MW
Lithos Rd A 11kVUK Power Networks2.3 km37 MW5.6 MW
Wood Lane 11kVUK Power Networks2.5 km35 MW33 MW
Aberdeen Pl A 11kVUK Power Networks2.9 km60 MW13 MW
Aberdeen Pl B 11kVUK Power Networks2.9 km45 MW2.8 MW

Thinking of connecting near London North West Connection Node A 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points