London North West Connection Node A 400kV: grid connection queue
London North West Connection Node A 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 1,000 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Amersham Main | Amersham 10 Renewables Limited | Solar + storage | 1,000 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kimberley Rd B 11kV | UK Power Networks | 0.7 km | 38 MW | 8.8 MW |
| Amberley Rd 11kV | UK Power Networks | 2.0 km | 118 MW | 29 MW |
| Lithos Rd A 11kV | UK Power Networks | 2.3 km | 37 MW | 5.6 MW |
| Wood Lane 11kV | UK Power Networks | 2.5 km | 35 MW | 33 MW |
| Aberdeen Pl A 11kV | UK Power Networks | 2.9 km | 60 MW | 13 MW |
| Aberdeen Pl B 11kV | UK Power Networks | 2.9 km | 45 MW | 2.8 MW |
Thinking of connecting near London North West Connection Node A 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- West London Connection Node B 132kV substation: 360 MW waiting
- London West Connection Node B 400kV: 200 MW waiting
- Mill Hill 275kV: 57 MW waiting
- London North West Connection Node B 400kV: 1,000 MW waiting
- London West Connection Node A 400kV: 200 MW waiting