West London Connection Node B 132kV substation: grid connection queue
West London Connection Node B 132kV substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 360 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Grovers Farm BESS | Bluestone Energy Ltd | Battery storage | 240 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| Brentford (SSEN-FBT624) -120MW BESS | Lightsource Renewable UK Development Limited | Battery storage | 120 | 31 Oct 2038 | Low | 31 Oct 2038 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Wood Lane 11kV | UK Power Networks | 0.8 km | 35 MW | 33 MW |
| Bulwer St 11kV | UK Power Networks | 1.0 km | 61 MW | 20 MW |
| Victoria Gdns 6.6kV | UK Power Networks | 1.2 km | 48 MW | 6.9 MW |
| Moscow Rd 6.6kV | UK Power Networks | 1.7 km | 25 MW | 17 MW |
| Moscow Rd 22kV | UK Power Networks | 1.7 km | 164 MW | 70 MW |
| Amberley Rd 11kV | UK Power Networks | 1.9 km | 118 MW | 29 MW |
Thinking of connecting near West London Connection Node B 132kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- London West Connection Node B 400kV: 200 MW waiting
- London North West Connection Node A 400kV: 1,000 MW waiting
- London North West Connection Node B 400kV: 1,000 MW waiting
- Mill Hill 275kV: 57 MW waiting
- London South Connection Node A 132kV: 480 MW waiting