London South Connection Node A 132kV: grid connection queue
London South Connection Node A 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 480 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Beddington 1 BESS | Bluestone Beddington 1 Ltd | Battery storage | 240 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
| Beddington 2 BESS | Bluestone Energy Ltd | Battery storage | 240 | 31 Oct 2037 | Low | 31 Oct 2037 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Verney Rd 11kV | UK Power Networks | 0.5 km | 52 MW | 9.1 MW |
| Neckinger 11kV | UK Power Networks | 1.4 km | 34 MW | 12 MW |
| Chadwick Road 33kV | UK Power Networks | 1.7 km | 105 MW | 44 MW |
| Tooley St 11kV | UK Power Networks | 2.5 km | 44 MW | 13 MW |
| Bengeworth Rd 11kV | UK Power Networks | 2.5 km | 58 MW | 13 MW |
| Bengeworth Rd Grid 33kV | UK Power Networks | 2.5 km | 143 MW | 40 MW |
Thinking of connecting near London South Connection Node A 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- London North East Connection Node A 400kV: 1,000 MW waiting
- Hurst 275kV: 228 MW waiting
- West London Connection Node B 132kV substation: 360 MW waiting
- London West Connection Node B 400kV: 200 MW waiting
- London North West Connection Node A 400kV: 1,000 MW waiting