London North East Connection Node A 400kV: grid connection queue

London North East Connection Node A 400kV · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

2 projects with 1,000 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 4 Apr 2033 to 31 Oct 2033.

2projects in the queue
1,000 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Waltham Cross Farm 2Waltham Cross 7 Renewables LimitedSolar + storage7004 Apr 2033Low4 Apr 2033Scopingnone
Waltham Cross BESSSHAW-ENERGI LTDBattery storage30031 Oct 2033Low31 Oct 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Farjeon Rd 11kVUK Power Networks1.1 km57 MW20 MW
Eltham Grid 11kVUK Power Networks1.8 km58 MW12 MW
Eltham High St 11kVUK Power Networks1.8 km39 MW12 MW
Eltham Grid 33kVUK Power Networks2.7 km109 MW48 MW
Dermody Rd 11kVUK Power Networks3.2 km37 MW9.8 MW
Old School Close 11kVUK Power Networks4.3 km106 MW70 MW

Thinking of connecting near London North East Connection Node A 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points