London North East Connection Node A 132kv: grid connection queue
London North East Connection Node A 132kv Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 200 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2038 to 31 Oct 2038.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Patmores (Mott Street) | INNOVA RENEWABLES LIMITED | Battery storage | 200 | 31 Oct 2038 | Low | 31 Oct 2038 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Axe St 11kV | UK Power Networks | 1.0 km | 51 MW | 18 MW |
| Clarks Rd B 11kV | UK Power Networks | 2.2 km | 57 MW | 13 MW |
| Nelson St 11kV | UK Power Networks | 2.5 km | 52 MW | 6.9 MW |
| Woodgrange Park 11kV | UK Power Networks | 3.0 km | 57 MW | 9.6 MW |
| Ley St B 11kV | UK Power Networks | 3.0 km | 49 MW | 14 MW |
| Barking West 11kV | UK Power Networks | 3.1 km | 40 MW | 18 MW |
Thinking of connecting near London North East Connection Node A 132kv?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Barking West: 100 MW waiting
- London North East Connection Node A 400kV: 1,000 MW waiting
- London North East Connection Node A: 1,000 MW waiting
- Hurst 275kV: 228 MW waiting
- London South Connection Node A 132kV: 480 MW waiting