London North East Connection Node A: grid connection queue

London North East Connection Node A · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 1,000 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 31 Oct 2031 to 31 Oct 2031.

1project in the queue
1,000 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Rye HouseRYE HOUSE 10 RENEWABLES LIMITEDSolar + storage1,00031 Oct 2031Medium31 Oct 2031Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Blackhorse Lane 11kVUK Power Networks0.3 km39 MW14 MW
Exeter Rd 11kVUK Power Networks1.8 km58 MW18 MW
Tottenham Grid 33kVUK Power Networks2.4 km80 MW42 MW
Bruce Gv Primary 11kVUK Power Networks2.4 km23 MW8.6 MW
Central Tottenham Primary 11kVUK Power Networks2.4 km29 MW6.5 MW
Tottenham Grid 11kVUK Power Networks2.4 km40 MW11 MW

Thinking of connecting near London North East Connection Node A?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.