Waltham Cross B 400kV: grid connection queue
Waltham Cross B 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
1 project with 250 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 29 Oct 2032 to 29 Oct 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Waltham Cross PV & BESS Sub | EPPING ENERGY PARK LIMITED | Solar + storage | 250 | 29 Oct 2032 | Low | 29 Oct 2032 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 1 later and 1 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 3 Nov 2026 | Waltham Cross PV & BESS Sub | 31 Oct 2029 | 29 Oct 2032 | +36 months |
| 13 Oct 2026 | Waltham Cross PV & BESS Sub | 31 Oct 2032 | 31 Oct 2029 | -36 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| The Cross 11kV | UK Power Networks | 0.5 km | 20 MW | 16 MW |
| Waltham Park 11kV | UK Power Networks | 0.9 km | 96 MW | 42 MW |
| Waltham Abbey Primary 11kV | UK Power Networks | 2.3 km | 12 MW | 5.3 MW |
| Brimsdown North Grid 33kV | UK Power Networks | 2.6 km | 107 MW | 19 MW |
| Brimsdown South Grid 11kV | UK Power Networks | 3.2 km | 41 MW | 7.2 MW |
| Turnford Primary 11kV | UK Power Networks | 3.7 km | 22 MW | 5.3 MW |
Thinking of connecting near Waltham Cross B 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Waltham Cross 400kV: 200 MW waiting
- London North East Connection Node A: 1,000 MW waiting
- Mill Hill 275kV: 57 MW waiting
- London North East Connection Node A 132kv: 200 MW waiting
- Letchmore Heath 132kV: 170 MW waiting