Letchmore Heath 132kV: grid connection queue

Letchmore Heath 132kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 170 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Jul 2030 to 31 Jul 2030.

1project in the queue
170 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Elstree Energy StorageELSTREE BATTERY STORAGE LIMITEDBattery storage17031 Jul 2030Medium31 Jul 2030Scoping1

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
13 Oct 2026Elstree Energy Storage1 Oct 202931 Jul 2030+10 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Elstree Primary 11kVUK Power Networks2.3 km40 MW13 MW
Hartspring Primary 11kVUK Power Networks3.8 km24 MW6.2 MW
Merryhill Primary 11kVUK Power Networks3.9 km19 MW3.8 MW
Rowley Ln Primary 11kVUK Power Networks4.2 km40 MW19 MW
Stonegrove Primary 11kVUK Power Networks4.5 km3.3 MW5.3 MW
Bushey Mill Grid 33kVUK Power Networks5.2 km111 MW50 MW

Thinking of connecting near Letchmore Heath 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points