Benzene

ELSTREE B 275KV SUBSTATION: grid connection queue

ELSTREE B 275KV SUBSTATION · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2037 to 31 Oct 2037.

1project in the queue
500 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Elstree BESS NPELSTREE FLEXPOWER LTDBattery storage50031 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Park St Primary 11kVUK Power Networks2.5 km8.8 MW9.5 MW
Shenley Primary 11kVUK Power Networks3.4 km1.4 MW8.8 MW
Bushey Mill Grid 33kVUK Power Networks4.6 km111 MW50 MW
Bushey Mill Grid 11kVUK Power Networks4.6 km100 MW40 MW
Hartspring Primary 11kVUK Power Networks4.7 km24 MW6.2 MW
Cell Barnes Grid 33kVUK Power Networks4.8 km108 MW52 MW

Thinking of connecting near ELSTREE B 275KV SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points