Waltham Cross 400kV: grid connection queue

Waltham Cross 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026

1 project with 200 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 4 Apr 2033 to 4 Apr 2033.

1project in the queue
200 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Waltham Cross FarmWaltham Cross 2 Renewables LimitedSolar + storage2004 Apr 2033Low4 Apr 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
The Cross 11kVUK Power Networks0.5 km20 MW16 MW
Waltham Park 11kVUK Power Networks0.9 km96 MW42 MW
Waltham Abbey Primary 11kVUK Power Networks2.3 km12 MW5.3 MW
Brimsdown North Grid 33kVUK Power Networks2.6 km107 MW19 MW
Brimsdown South Grid 11kVUK Power Networks3.2 km41 MW7.2 MW
Turnford Primary 11kVUK Power Networks3.7 km22 MW5.3 MW

Thinking of connecting near Waltham Cross 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points