Rowdown 400kV: grid connection queue
Rowdown 400kV Substation · National Grid Electricity Transmission (England and Wales) · register of 26 November 2026
2 projects with 649 MW are waiting to connect here (largest by capacity: solar + storage, battery storage). Contracted dates run from 22 Oct 2031 to 22 Oct 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Littlebrook GEC (Ethos Green) | LITTLEBROOK GREEN ENERGY CENTRE LTD | Solar + storage | 400 | 22 Oct 2031 | Medium | 22 Oct 2031 | Awaiting Consents | 1 |
| Mickleham Energy Storage | BW ESS DEVELOPMENT UK LIMITED | Battery storage | 249 | 22 Oct 2031 | Medium | 22 Oct 2031 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| West Wickham 11kV | UK Power Networks | 1.7 km | 25 MW | 4.2 MW |
| Addington Grid 33kV | UK Power Networks | 2.5 km | 106 MW | 14 MW |
| Addington Local 11kV | UK Power Networks | 2.6 km | 24 MW | 6.3 MW |
| Addington Grid 11kV | UK Power Networks | 2.6 km | 11 MW | 12 MW |
| Selsdon 11kV | UK Power Networks | 4.1 km | 24 MW | 7.5 MW |
| Shirley 11kV | UK Power Networks | 4.2 km | 24 MW | 7.3 MW |
Thinking of connecting near Rowdown 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Hurst 275kV: 228 MW waiting
- London North East Connection Node A 400kV: 1,000 MW waiting
- London South Connection Node A 132kV: 480 MW waiting
- Northfleet East 400kV: 50 MW waiting
- Barking West: 100 MW waiting