Kilmarnock South 400kV: grid connection queue

Kilmarnock South 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2027 to 30 Apr 2027.

1project in the queue
500 MWwaiting to connect
300 MWalready connected
500 MWholding Gate 2
0date moves since 2 Jun 2026
500 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Kilmarnock South Battery StorageKilmarnock Energy Centre LimitedBattery storage50030 Apr 2027High29 Apr 2029Consents Approved2

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Kilmarnock MainSP Energy Networks3.1 km27 MW12 MW
Queens DriveSP Energy Networks3.5 km15 MW
Langlands StreetSP Energy Networks4.7 km23 MW11 MW
GrassyardsSP Energy Networks4.7 km11 MW
DrumleySP Energy Networks9.1 km11 MW4.7 MW
MauchlineSP Energy Networks9.2 km11 MW4.6 MW

Thinking of connecting near Kilmarnock South 400kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points