Kilmarnock South 400kV: grid connection queue
Kilmarnock South 400kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 500 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2027 to 30 Apr 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Kilmarnock South Battery Storage | Kilmarnock Energy Centre Limited | Battery storage | 500 | 30 Apr 2027 | High | 29 Apr 2029 | Consents Approved | 2 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kilmarnock Main | SP Energy Networks | 3.1 km | 27 MW | 12 MW |
| Queens Drive | SP Energy Networks | 3.5 km | 15 MW | |
| Langlands Street | SP Energy Networks | 4.7 km | 23 MW | 11 MW |
| Grassyards | SP Energy Networks | 4.7 km | 11 MW | |
| Drumley | SP Energy Networks | 9.1 km | 11 MW | 4.7 MW |
| Mauchline | SP Energy Networks | 9.2 km | 11 MW | 4.6 MW |
Thinking of connecting near Kilmarnock South 400kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Boydston 400kV substation: 350 MW waiting
- Kilmarnock Town 275/33kV: 60 MW waiting
- Kilwinning 132/33kV: 190 MW waiting
- Whitelee Extension 275/33kV: 89 MW waiting
- Killoch BESS 132kV: 150 MW waiting