Killoch BESS 132kV: grid connection queue

Killoch BESS 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 150 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Sep 2030 to 30 Sep 2030.

1project in the queue
150 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Killoch BESSRenewable Energy Systems LimitedBattery storage15030 Sep 2030Medium30 Sep 2030Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Killoch CollierySP Energy Networks0.1 km27 MW8.3 MW
MauchlineSP Energy Networks6.2 km11 MW4.6 MW
CumnockSP Energy Networks8.2 km14 MW
DrumleySP Energy Networks8.3 km11 MW4.7 MW
LethanhillSP Energy Networks11.5 km25 MW14 MW
Old Bridge RoadSP Energy Networks12.3 km15 MW

Thinking of connecting near Killoch BESS 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points