Ayr 275/33kV: grid connection queue

Ayr 275/33kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 150 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Oct 2028 to 30 Oct 2028.

1project in the queue
150 MWwaiting to connect
0 MWalready connected
150 MWholding Gate 2
1date moves since 2 Jun 2026
150 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Ayr Energy StorageKXP ALPHA I LIMITEDBattery storage15030 Oct 2028High30 Oct 2030Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
30 Jun 2026Ayr Energy Storage30 Oct 202730 Oct 2028+12 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Old Bridge RoadSP Energy Networks2.1 km15 MW
Mill StreetSP Energy Networks2.4 km25 MW6.3 MW
GlengallSP Energy Networks3.1 km24 MW9 MW
DrumleySP Energy Networks6.2 km11 MW4.7 MW
MonktonSP Energy Networks6.6 km25 MW6.1 MW
TroonSP Energy Networks10.7 km24 MW3.1 MW

Thinking of connecting near Ayr 275/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points