Ayr: grid connection queue
Ayr GSP · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 60 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 30 Aug 2028 to 30 Aug 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Knockkippen Energy Park | KNOCKKIPPEN WIND ENERGY LIMITED | Mixed and other | 60 | 30 Aug 2028 | High | 14 Apr 2031 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Old Bridge Road | SP Energy Networks | 2.1 km | 15 MW | |
| Mill Street | SP Energy Networks | 2.4 km | 25 MW | 6.3 MW |
| Glengall | SP Energy Networks | 3.1 km | 24 MW | 9 MW |
| Drumley | SP Energy Networks | 6.2 km | 11 MW | 4.7 MW |
| Monkton | SP Energy Networks | 6.6 km | 25 MW | 6.1 MW |
| Troon | SP Energy Networks | 10.7 km | 24 MW | 3.1 MW |
Thinking of connecting near Ayr?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Ayr 275/33kV: 400 MW waiting
- Ayr 275/33kV: 150 MW waiting
- South Kyle 2 132/33kV: 92 MW waiting
- Killoch BESS 132kV: 150 MW waiting
- Sclenteuch Energy Park 132kV: 54 MW waiting