Ayr: grid connection queue

Ayr GSP · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 60 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 30 Aug 2028 to 30 Aug 2028.

1project in the queue
60 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
60 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Knockkippen Energy ParkKNOCKKIPPEN WIND ENERGY LIMITEDMixed and other6030 Aug 2028High14 Apr 2031Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Old Bridge RoadSP Energy Networks2.1 km15 MW
Mill StreetSP Energy Networks2.4 km25 MW6.3 MW
GlengallSP Energy Networks3.1 km24 MW9 MW
DrumleySP Energy Networks6.2 km11 MW4.7 MW
MonktonSP Energy Networks6.6 km25 MW6.1 MW
TroonSP Energy Networks10.7 km24 MW3.1 MW

Thinking of connecting near Ayr?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points