Sclenteuch Energy Park 132kV: grid connection queue

Sclenteuch Energy Park 132kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 54 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.

1project in the queue
54 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
54 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Sclenteuch Energy ParkSCLENTEUCH ENERGY LIMITEDOnshore wind + storage5431 Oct 2029High17 Sep 2031Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LethanhillSP Energy Networks3.5 km25 MW14 MW
Maybole (Primary)SP Energy Networks11.6 km12 MW2.6 MW
GlengallSP Energy Networks12.5 km24 MW9 MW
Killoch CollierySP Energy Networks15.1 km27 MW8.3 MW
Mill StreetSP Energy Networks15.6 km25 MW6.3 MW
Old Bridge RoadSP Energy Networks16.5 km15 MW

Thinking of connecting near Sclenteuch Energy Park 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points