Carrick Wind Farm Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 84 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 1 Apr 2030 to 1 Apr 2030.

1project in the queue
84 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
84 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Carrick Wind FarmScottishPower Renewables (UK) LimitedOnshore wind841 Apr 2030High16 Feb 2032Awaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LethanhillSP Energy Networks14.4 km25 MW14 MW
Maybole (Primary)SP Energy Networks15.2 km12 MW2.6 MW
GirvanSP Energy Networks17.2 km6.9 MW12 MW

Thinking of connecting near Carrick Wind Farm?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points