Maybole: grid connection queue
Maybole GSP · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 213 MW are waiting to connect here (largest by capacity: onshore wind + storage, onshore wind). Contracted dates run from 31 Oct 2032 to 31 Oct 2032.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Assel Valley Extension Wind Farm | Renantis UK Limited | Onshore wind + storage | 175 | 31 Oct 2032 | Low | 31 Oct 2032 | Scoping | 1 |
| Craigdow Hill Wind Farm | ABEI ENERGY LIMITED | Onshore wind | 38 | 31 Oct 2032 | Low | 31 Oct 2032 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Girvan | SP Energy Networks | 9.3 km | 6.9 MW | 12 MW |
| Pinwherry | SP Energy Networks | 9.9 km | 7 MW | 5.4 MW |
| Maybole (Primary) | SP Energy Networks | 16.0 km | 12 MW | 2.6 MW |
Thinking of connecting near Maybole?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Maybole 132/33kV: 92 MW waiting
- Knockodhar Wind Farm 132kV: 120 MW waiting
- Clauchrie 132/33KV: 108 MW waiting
- Carrick Wind Farm: 84 MW waiting
- Knockcronal Wind Farm 33kV: 59 MW waiting