Knockodhar Wind Farm 132kV: grid connection queue

Knockodhar Wind Farm 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 120 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Apr 2028 to 30 Apr 2028.

1project in the queue
120 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
120 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Knockodhar Wind FarmREG KNOCKODHAR LIMITEDOnshore wind12030 Apr 2028High28 Jun 2030Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
GirvanSP Energy Networks9.3 km6.9 MW12 MW
PinwherrySP Energy Networks10.1 km7 MW5.4 MW
Maybole (Primary)SP Energy Networks15.9 km12 MW2.6 MW

Thinking of connecting near Knockodhar Wind Farm 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.