Dersalloch 132/33kV: grid connection queue

Dersalloch 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 11 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2027 to 31 Oct 2027.

1project in the queue
11 MWwaiting to connect
69 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
11 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Dersalloch Wind Farm ExtensionScottishPower Renewables (UK) LimitedBattery storage1131 Oct 2027High30 Oct 2029Scopingnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LethanhillSP Energy Networks5.1 km25 MW14 MW
Maybole (Primary)SP Energy Networks14.7 km12 MW2.6 MW
GlengallSP Energy Networks15.5 km24 MW9 MW
Killoch CollierySP Energy Networks15.8 km27 MW8.3 MW
New CumnockSP Energy Networks17.3 km-67 MW7.8 MW
Mill StreetSP Energy Networks18.6 km25 MW6.3 MW

Thinking of connecting near Dersalloch 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points