Enoch Hill 2 Wind Farm 33kV: grid connection queue

Enoch Hill 2 Wind Farm 33kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 10 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 30 Apr 2027 to 30 Apr 2027.

1project in the queue
10 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
10 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Enoch Hill 2 Wind FarmRWE Renewables UK Onshore Wind LimitedOnshore wind + storage1030 Apr 2027High27 Jun 2029Awaiting Consents1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
LethanhillSP Energy Networks5.3 km25 MW14 MW
Killoch CollierySP Energy Networks14.8 km27 MW8.3 MW
New CumnockSP Energy Networks15.4 km-67 MW7.8 MW
GlengallSP Energy Networks16.1 km24 MW9 MW
Maybole (Primary)SP Energy Networks16.3 km12 MW2.6 MW
CumnockSP Energy Networks17.6 km14 MW

Thinking of connecting near Enoch Hill 2 Wind Farm 33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points