Benbrack Wind Farm 132/33kV: grid connection queue

Benbrack Wind Farm 132/33kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 42 MW is waiting to connect here (largest by capacity: mixed and other). Contracted dates run from 31 Aug 2029 to 31 Aug 2029.

1project in the queue
42 MWwaiting to connect
72 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Lamford HillBENBRACK WIND FARM LIMITEDMixed and other4231 Aug 2029Medium31 Aug 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
New CumnockSP Energy Networks13.7 km-67 MW7.8 MW
Kendoon HydroSP Energy Networks13.8 km31 MW27 MW
LethanhillSP Energy Networks15.6 km25 MW14 MW
Carsfad HydroSP Energy Networks15.8 km30 MW28 MW
Earlstoun HydroSP Energy Networks19.3 km16 MW12 MW

Thinking of connecting near Benbrack Wind Farm 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points