Quantans Hill 132kV: grid connection queue
Quantans Hill 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 145 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 2 Jul 2029 to 31 Oct 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Quantans Hill Wind Farm | VATTENFALL WIND POWER LTD | Onshore wind | 95 | 2 Jul 2029 | High | 19 May 2031 | Scoping | none |
| Cornharrow Wind Farm | ENERGYFARM UK CORNHARROW LLP | Onshore wind | 50 | 31 Oct 2030 | High | 16 Sep 2032 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kendoon Hydro | SP Energy Networks | 5.4 km | 31 MW | 27 MW |
| Carsfad Hydro | SP Energy Networks | 7.7 km | 30 MW | 28 MW |
| Earlstoun Hydro | SP Energy Networks | 11.1 km | 16 MW | 12 MW |
| Glenlee Hydro | SP Energy Networks | 12.5 km | 30 MW | 28 MW |
| New Cumnock | SP Energy Networks | 18.6 km | -67 MW | 7.8 MW |
Thinking of connecting near Quantans Hill 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Shepards Rig 132/33kV: 85 MW waiting
- Manquhill Wind Farm 132/33kV: 56 MW waiting
- Dun Hill 132/33kV: 110 MW waiting
- Wether Hill 132/33KV: 66 MW waiting
- SPT Margree collector substation: 145 MW waiting