SPT Margree collector substation: grid connection queue

SPT Margree collector substation · SP Transmission (southern Scotland) · register of 26 November 2026

3 projects with 145 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.

3projects in the queue
145 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
145 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Fell Wind FarmENERGYFARM UK FELL LLPOnshore wind5031 Oct 2029High17 Sep 2031Scopingnone
Margree Wind FarmENERGYFARM UK MARGREE LLPOnshore wind5031 Oct 2029High17 Sep 2031Awaiting Consentsnone
Glenshimmeroch WindfarmENERGYFARM UK GLENSHIMMEROCH LLPOnshore wind4531 Oct 2029High17 Sep 2031Consents Approvednone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Carsfad HydroSP Energy Networks7.0 km30 MW28 MW
Kendoon HydroSP Energy Networks7.1 km31 MW27 MW
Earlstoun HydroSP Energy Networks7.6 km16 MW12 MW
Glenlee HydroSP Energy Networks9.1 km30 MW28 MW
PenpontSP Energy Networks19.2 km3.5 MW

Thinking of connecting near SPT Margree collector substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.