Divot Hill 132/33 kV: grid connection queue
Divot Hill 132/33 kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 63 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 Oct 2036 to 31 Oct 2036.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Divot Hill Wind Farm | ENERGYFARM DIVOT HILL LTD | Onshore wind + storage | 63 | 31 Oct 2036 | Low | 31 Oct 2036 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Carsfad Hydro | SP Energy Networks | 5.1 km | 30 MW | 28 MW |
| Earlstoun Hydro | SP Energy Networks | 5.3 km | 16 MW | 12 MW |
| Kendoon Hydro | SP Energy Networks | 5.7 km | 31 MW | 27 MW |
| Glenlee Hydro | SP Energy Networks | 6.7 km | 30 MW | 28 MW |
Thinking of connecting near Divot Hill 132/33 kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- SPT Margree collector substation: 145 MW waiting
- Margree 132/33kV Collector: 68 MW waiting
- Quantans Hill 132kV: 145 MW waiting
- Shepards Rig 132/33kV: 85 MW waiting
- Wether Hill 132/33KV: 66 MW waiting