Shepards Rig 132/33kV: grid connection queue
Shepards Rig 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 85 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 May 2030 to 30 May 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Shepherds Rig Wind Farm | SETT WIND DEVELOPMENT LIMITED | Onshore wind | 85 | 30 May 2030 | High | 15 Apr 2032 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 30 Jun 2026 | Shepherds Rig Wind Farm | 30 Jul 2024 | 30 May 2030 | +70 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Kendoon Hydro | SP Energy Networks | 6.1 km | 31 MW | 27 MW |
| Carsfad Hydro | SP Energy Networks | 8.4 km | 30 MW | 28 MW |
| Earlstoun Hydro | SP Energy Networks | 11.7 km | 16 MW | 12 MW |
| Glenlee Hydro | SP Energy Networks | 13.2 km | 30 MW | 28 MW |
| New Cumnock | SP Energy Networks | 18.1 km | -67 MW | 7.8 MW |
Thinking of connecting near Shepards Rig 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Quantans Hill 132kV: 145 MW waiting
- Manquhill Wind Farm 132/33kV: 56 MW waiting
- Wether Hill 132/33KV: 66 MW waiting
- Dun Hill 132/33kV: 110 MW waiting
- SPT Margree collector substation: 145 MW waiting