Shepards Rig 132/33kV: grid connection queue

Shepards Rig 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 85 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 May 2030 to 30 May 2030.

1project in the queue
85 MWwaiting to connect
0 MWalready connected
85 MWholding Gate 2
1date moves since 2 Jun 2026
85 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Shepherds Rig Wind FarmSETT WIND DEVELOPMENT LIMITEDOnshore wind8530 May 2030High15 Apr 2032Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
30 Jun 2026Shepherds Rig Wind Farm30 Jul 202430 May 2030+70 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Kendoon HydroSP Energy Networks6.1 km31 MW27 MW
Carsfad HydroSP Energy Networks8.4 km30 MW28 MW
Earlstoun HydroSP Energy Networks11.7 km16 MW12 MW
Glenlee HydroSP Energy Networks13.2 km30 MW28 MW
New CumnockSP Energy Networks18.1 km-67 MW7.8 MW

Thinking of connecting near Shepards Rig 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points