Dun Hill 132/33kV: grid connection queue
Dun Hill 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 110 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 1 Jun 2026 to 30 Jun 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Windy Standard III Wind Farm | Windy Standard III Limited | Onshore wind | 88 | 1 Jun 2026 | n/a | Consents Approved | 2 | |
| Windy Standard 1 Repower | FRED OLSEN RENEWABLES LIMITED | Onshore wind | 22 | 30 Jun 2031 | High | 16 May 2033 | Scoping | none |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 23 Jun 2026 | Windy Standard III Wind Farm | 1 Jun 2026 | 31 Oct 2027 | +17 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| New Cumnock | SP Energy Networks | 11.4 km | -67 MW | 7.8 MW |
| Kendoon Hydro | SP Energy Networks | 12.9 km | 31 MW | 27 MW |
| Carsfad Hydro | SP Energy Networks | 15.2 km | 30 MW | 28 MW |
| Lethanhill | SP Energy Networks | 18.5 km | 25 MW | 14 MW |
| Earlstoun Hydro | SP Energy Networks | 18.8 km | 16 MW | 12 MW |
| Cumnock | SP Energy Networks | 19.5 km | 14 MW |
Thinking of connecting near Dun Hill 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Benbrack Wind Farm 132/33kV: 42 MW waiting
- Manquhill Wind Farm 132/33kV: 56 MW waiting
- Quantans Hill 132kV: 145 MW waiting
- Shepards Rig 132/33kV: 85 MW waiting
- Euchanhead 132kV: 112 MW waiting