Dun Hill 132/33kV: grid connection queue

Dun Hill 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 110 MW are waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 1 Jun 2026 to 30 Jun 2031.

2projects in the queue
110 MWwaiting to connect
62 MWalready connected
88 MWholding Gate 2
1date moves since 2 Jun 2026
22 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Windy Standard III Wind FarmWindy Standard III LimitedOnshore wind881 Jun 2026n/aConsents Approved2
Windy Standard 1 RepowerFRED OLSEN RENEWABLES LIMITEDOnshore wind2230 Jun 2031High16 May 2033Scopingnone

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
23 Jun 2026Windy Standard III Wind Farm1 Jun 202631 Oct 2027+17 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
New CumnockSP Energy Networks11.4 km-67 MW7.8 MW
Kendoon HydroSP Energy Networks12.9 km31 MW27 MW
Carsfad HydroSP Energy Networks15.2 km30 MW28 MW
LethanhillSP Energy Networks18.5 km25 MW14 MW
Earlstoun HydroSP Energy Networks18.8 km16 MW12 MW
CumnockSP Energy Networks19.5 km14 MW

Thinking of connecting near Dun Hill 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points