Euchanhead 132kV: grid connection queue

Euchanhead 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 112 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 29 Oct 2030 to 29 Oct 2030.

1project in the queue
112 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
112 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Euchanhead Wind FarmScottishPower Renewables (UK) LimitedOnshore wind11229 Oct 2030High14 Sep 2032Awaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
New CumnockSP Energy Networks10.0 km-67 MW7.8 MW
FauldheadSP Energy Networks10.8 km9.4 MW5.7 MW
Kendoon HydroSP Energy Networks17.4 km31 MW27 MW
CumnockSP Energy Networks18.6 km14 MW
Carsfad HydroSP Energy Networks19.6 km30 MW28 MW

Thinking of connecting near Euchanhead 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points