Sandyknowe 132/33kV: grid connection queue
Sandyknowe 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 22 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2027 to 31 Oct 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Sandy Knowe Wind Farm | SANDY KNOWE WIND FARM LIMITED | Onshore wind | 22 | 31 Oct 2027 | High | 28 Dec 2029 | Awaiting Consents | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Fauldhead | SP Energy Networks | 3.5 km | 9.4 MW | 5.7 MW |
| New Cumnock | SP Energy Networks | 10.5 km | -67 MW | 7.8 MW |
| Cronberry | SP Energy Networks | 16.1 km | 7.9 MW | 7.3 MW |
| Cumnock | SP Energy Networks | 16.6 km | 14 MW |
Thinking of connecting near Sandyknowe 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- ROWANCRAIG WIND FARM 33KV SUBSTATION: 40 MW waiting
- Glenmuckloch 132/33kV: 34 MW waiting
- Lethans Collector 132kV: 85 MW waiting
- Lethans Collector: 132 MW waiting
- Euchanhead 132kV: 112 MW waiting