Glenmuckloch 132/33kV: grid connection queue
Glenmuckloch 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 34 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 May 2029 to 31 May 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Glenmuckloch Wind Farm | GLENMUCKLOCH RENEWABLE ENERGY LIMITED | Onshore wind | 34 | 31 May 2029 | High | 17 Apr 2031 | Consents Approved | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Fauldhead | SP Energy Networks | 4.2 km | 9.4 MW | 5.7 MW |
| New Cumnock | SP Energy Networks | 11.4 km | -67 MW | 7.8 MW |
| Cronberry | SP Energy Networks | 11.4 km | 7.9 MW | 7.3 MW |
| Cumnock | SP Energy Networks | 14.6 km | 14 MW | |
| Douglas West | SP Energy Networks | 19.3 km | 22 MW | 15 MW |
Thinking of connecting near Glenmuckloch 132/33kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Lethans Collector: 132 MW waiting
- Glenmuckloch 132kV: 668 MW waiting
- Lethans Collector 132kV: 85 MW waiting
- Sandyknowe 132/33kV: 22 MW waiting
- ROWANCRAIG WIND FARM 33KV SUBSTATION: 40 MW waiting