Lethans Collector: grid connection queue

Lethans Collector Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 132 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.

1project in the queue
132 MWwaiting to connect
0 MWalready connected
132 MWholding Gate 2
1date moves since 2 Jun 2026
132 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Lethans Wind FarmLethans Wind Farm LimitedOnshore wind13231 Oct 2029High17 Sep 2031Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
7 Jul 2026Lethans Wind Farm30 Jun 202730 Oct 2029+28 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
FauldheadSP Energy Networks5.9 km9.4 MW5.7 MW
New CumnockSP Energy Networks9.8 km-67 MW7.8 MW
CronberrySP Energy Networks10.4 km7.9 MW7.3 MW
CumnockSP Energy Networks12.6 km14 MW

Thinking of connecting near Lethans Collector?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.