New Cumnock 275/132kV: grid connection queue

New Cumnock 275/132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 450 MW is waiting to connect here (largest by capacity: solar + storage). Contracted dates run from 30 Oct 2033 to 30 Oct 2033.

1project in the queue
450 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
New Cumnock BESSNEW CUMNOCK BESS LTDSolar + storage45030 Oct 2033Low30 Oct 2033Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
New CumnockSP Energy Networks3.4 km-67 MW7.8 MW
CumnockSP Energy Networks7.9 km14 MW
FauldheadSP Energy Networks11.3 km9.4 MW5.7 MW
CronberrySP Energy Networks12.4 km7.9 MW7.3 MW
Killoch CollierySP Energy Networks15.0 km27 MW8.3 MW
MauchlineSP Energy Networks17.4 km11 MW4.6 MW

Thinking of connecting near New Cumnock 275/132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points