Coylton 275kV substation: grid connection queue

Coylton 275kV substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 450 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2026 to 30 Apr 2026.

1project in the queue
450 MWwaiting to connect
0 MWalready connected
450 MWholding Gate 2
1date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Coylton 275kV Greener Grid ParkCOYLTON ENERGY LIMITEDBattery storage45030 Apr 2026n/aConsents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
4 Aug 2026Coylton 275kV Greener Grid Park28 Feb 202618 May 2026+3 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
New CumnockSP Energy Networks3.0 km-67 MW7.8 MW
CumnockSP Energy Networks6.0 km14 MW
Killoch CollierySP Energy Networks12.3 km27 MW8.3 MW
CronberrySP Energy Networks13.3 km7.9 MW7.3 MW
FauldheadSP Energy Networks14.2 km9.4 MW5.7 MW
MauchlineSP Energy Networks15.3 km11 MW4.6 MW

Thinking of connecting near Coylton 275kV substation?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points