Coylton 275kV substation: grid connection queue
Coylton 275kV substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 450 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 Apr 2026 to 30 Apr 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Coylton 275kV Greener Grid Park | COYLTON ENERGY LIMITED | Battery storage | 450 | 30 Apr 2026 | n/a | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 4 Aug 2026 | Coylton 275kV Greener Grid Park | 28 Feb 2026 | 18 May 2026 | +3 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| New Cumnock | SP Energy Networks | 3.0 km | -67 MW | 7.8 MW |
| Cumnock | SP Energy Networks | 6.0 km | 14 MW | |
| Killoch Colliery | SP Energy Networks | 12.3 km | 27 MW | 8.3 MW |
| Cronberry | SP Energy Networks | 13.3 km | 7.9 MW | 7.3 MW |
| Fauldhead | SP Energy Networks | 14.2 km | 9.4 MW | 5.7 MW |
| Mauchline | SP Energy Networks | 15.3 km | 11 MW | 4.6 MW |
Thinking of connecting near Coylton 275kV substation?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Coylton 275/132kV: 100 MW waiting
- New Cumnock A 132kV: 80 MW waiting
- New Cumnock North 132kV: 80 MW waiting
- New Cumnock 275/132kV: 450 MW waiting
- Lethans Collector 132kV: 85 MW waiting