Lethans Collector 132kV: grid connection queue

Lethans Collector 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 85 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.

1project in the queue
85 MWwaiting to connect
0 MWalready connected
85 MWholding Gate 2
1date moves since 2 Jun 2026
85 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Lethans Wind Farm ExtensionLETHANS EAST WIND FARM LIMITEDOnshore wind8531 Oct 2029High17 Sep 2031Consents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
7 Jul 2026Lethans Wind Farm Extension30 Oct 202730 Oct 2029+24 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
New CumnockSP Energy Networks6.7 km-67 MW7.8 MW
FauldheadSP Energy Networks7.3 km9.4 MW5.7 MW
CumnockSP Energy Networks11.3 km14 MW
CronberrySP Energy Networks12.1 km7.9 MW7.3 MW
Killoch CollierySP Energy Networks18.9 km27 MW8.3 MW

Thinking of connecting near Lethans Collector 132kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.