Lethans Collector 132kV: grid connection queue
Lethans Collector 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 85 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 Oct 2029 to 31 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Lethans Wind Farm Extension | LETHANS EAST WIND FARM LIMITED | Onshore wind | 85 | 31 Oct 2029 | High | 17 Sep 2031 | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 7 Jul 2026 | Lethans Wind Farm Extension | 30 Oct 2027 | 30 Oct 2029 | +24 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| New Cumnock | SP Energy Networks | 6.7 km | -67 MW | 7.8 MW |
| Fauldhead | SP Energy Networks | 7.3 km | 9.4 MW | 5.7 MW |
| Cumnock | SP Energy Networks | 11.3 km | 14 MW | |
| Cronberry | SP Energy Networks | 12.1 km | 7.9 MW | 7.3 MW |
| Killoch Colliery | SP Energy Networks | 18.9 km | 27 MW | 8.3 MW |
Thinking of connecting near Lethans Collector 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Lethans Collector: 132 MW waiting
- New Cumnock 275/132kV: 450 MW waiting
- Glenmuckloch 132kV: 668 MW waiting
- Glenmuckloch 132/33kV: 34 MW waiting
- Sandyknowe 132/33kV: 22 MW waiting