Coylton 275/132kV: grid connection queue
Coylton 275/132kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 100 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 31 Oct 2027 to 31 Oct 2027.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Drongan Battery Storage | Drongan Battery Storage Ltd | Battery storage | 100 | 31 Oct 2027 | High | 30 Oct 2029 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| New Cumnock | SP Energy Networks | 3.0 km | -67 MW | 7.8 MW |
| Cumnock | SP Energy Networks | 6.0 km | 14 MW | |
| Killoch Colliery | SP Energy Networks | 12.3 km | 27 MW | 8.3 MW |
| Cronberry | SP Energy Networks | 13.3 km | 7.9 MW | 7.3 MW |
| Fauldhead | SP Energy Networks | 14.2 km | 9.4 MW | 5.7 MW |
| Mauchline | SP Energy Networks | 15.3 km | 11 MW | 4.6 MW |
Thinking of connecting near Coylton 275/132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Coylton 275kV substation: 450 MW waiting
- New Cumnock A 132kV: 80 MW waiting
- New Cumnock North 132kV: 80 MW waiting
- New Cumnock 275/132kV: 450 MW waiting
- Lethans Collector 132kV: 85 MW waiting