New Cumnock A 132kV: grid connection queue
New Cumnock A 132kV · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 80 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Apr 2028 to 30 Apr 2028.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Breezy Hill Wind Farm | BROCKWELL ENERGY LIMITED | Onshore wind | 80 | 30 Apr 2028 | High | 28 Jun 2030 | Scoping | none |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| New Cumnock | SP Energy Networks | 1.9 km | -67 MW | 7.8 MW |
| Cumnock | SP Energy Networks | 7.6 km | 14 MW | |
| Fauldhead | SP Energy Networks | 12.8 km | 9.4 MW | 5.7 MW |
| Cronberry | SP Energy Networks | 13.8 km | 7.9 MW | 7.3 MW |
| Killoch Colliery | SP Energy Networks | 14.0 km | 27 MW | 8.3 MW |
| Mauchline | SP Energy Networks | 17.0 km | 11 MW | 4.6 MW |
Thinking of connecting near New Cumnock A 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- New Cumnock North 132kV: 80 MW waiting
- Coylton 275kV substation: 450 MW waiting
- Coylton 275/132kV: 100 MW waiting
- New Cumnock 275/132kV: 450 MW waiting
- Lethans Collector 132kV: 85 MW waiting