ROWANCRAIG WIND FARM 33KV SUBSTATION: grid connection queue
ROWANCRAIG WIND FARM 33KV SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 40 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 31 May 2030 to 31 May 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Rowancraig Wind Farm | Koehler Renewable Energy UK Limited | Onshore wind | 40 | 31 May 2030 | High | 16 Apr 2032 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Rowancraig Wind Farm | 30 Oct 2028 | 31 May 2030 | +19 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Fauldhead | SP Energy Networks | 4.8 km | 9.4 MW | 5.7 MW |
| New Cumnock | SP Energy Networks | 14.0 km | -67 MW | 7.8 MW |
| Penpont | SP Energy Networks | 18.1 km | 3.5 MW | |
| Cronberry | SP Energy Networks | 19.8 km | 7.9 MW | 7.3 MW |
Thinking of connecting near ROWANCRAIG WIND FARM 33KV SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Sandyknowe 132/33kV: 22 MW waiting
- Sanquhar II Wind Farm: 250 MW waiting
- Euchanhead 132kV: 112 MW waiting
- Glenmuckloch 132/33kV: 34 MW waiting
- Lethans Collector 132kV: 85 MW waiting