Sanquhar II Wind Farm: grid connection queue
Sanquhar II Wind Farm Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 250 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 17 Oct 2026 to 17 Oct 2026.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Sanquhar II Wind Farm | SANQUHAR II COMMUNITY WIND CO LTD | Onshore wind | 250 | 17 Oct 2026 | n/a | Consents Approved | 2 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 10 Nov 2026 | Sanquhar II Wind Farm | 28 Feb 2027 | 26 Nov 2027 | +9 months |
| 10 Nov 2026 | Sanquhar II Wind Farm | 31 Jul 2026 | 17 Oct 2026 | +3 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Fauldhead | SP Energy Networks | 5.8 km | 9.4 MW | 5.7 MW |
| Penpont | SP Energy Networks | 17.1 km | 3.5 MW | |
| New Cumnock | SP Energy Networks | 18.6 km | -67 MW | 7.8 MW |
Thinking of connecting near Sanquhar II Wind Farm?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- ROWANCRAIG WIND FARM 33KV SUBSTATION: 40 MW waiting
- NLEI Windfarm 132/33kV substation: 151 MW waiting
- Sandyknowe 132/33kV: 22 MW waiting
- Glenglass 132/33kV: 60 MW waiting
- Glenmuckloch 132/33kV: 34 MW waiting