Sanquhar II Wind Farm: grid connection queue

Sanquhar II Wind Farm Substation · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 250 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 17 Oct 2026 to 17 Oct 2026.

1project in the queue
250 MWwaiting to connect
0 MWalready connected
250 MWholding Gate 2
2date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Sanquhar II Wind FarmSANQUHAR II COMMUNITY WIND CO LTDOnshore wind25017 Oct 2026n/aConsents Approved2

Dates that moved

Since 2 Jun 2026, connection dates here moved by a month or more 2 times: 2 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.

Week seenProjectWasNowChange
10 Nov 2026Sanquhar II Wind Farm28 Feb 202726 Nov 2027+9 months
10 Nov 2026Sanquhar II Wind Farm31 Jul 202617 Oct 2026+3 months

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
FauldheadSP Energy Networks5.8 km9.4 MW5.7 MW
PenpontSP Energy Networks17.1 km3.5 MW
New CumnockSP Energy Networks18.6 km-67 MW7.8 MW

Thinking of connecting near Sanquhar II Wind Farm?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points