Glenglass 132/33kV: grid connection queue

Glenglass 132/33kV · SP Transmission (southern Scotland) · register of 26 November 2026

1 project with 60 MW is waiting to connect here (largest by capacity: onshore wind + storage). Contracted dates run from 31 May 2030 to 31 May 2030.

1project in the queue
60 MWwaiting to connect
65 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
60 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Cloud Hill WindfarmCloud Hill Windfarm LimitedOnshore wind + storage6031 May 2030High16 Apr 2032Awaiting Consentsnone

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
FauldheadSP Energy Networks13.2 km9.4 MW5.7 MW
Douglas WestSP Energy Networks18.5 km22 MW15 MW
PenpontSP Energy Networks18.8 km3.5 MW

Thinking of connecting near Glenglass 132/33kV?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points