ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION: grid connection queue

ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 75 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 26 Oct 2029 to 26 Oct 2029.

2projects in the queue
75 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Elvanfoot (50MW) Energy StorageELVANFOOT ENERGY STORAGE 2 LIMITEDBattery storage5026 Oct 2029Medium26 Oct 2029Scoping1
Elvanfoot (25MW) Energy StorageELVANFOOT ENERGY STORAGE 3 LIMITEDBattery storage2526 Oct 2029Medium26 Oct 2029Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Douglas WestSP Energy Networks19.0 km22 MW15 MW
SymingtonSP Energy Networks19.0 km12 MW3.3 MW
MoffatSP Energy Networks19.5 km8.5 MW3.6 MW

Thinking of connecting near ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.

Nearby connection points