ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION: grid connection queue
ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION · SP Transmission (southern Scotland) · register of 26 November 2026
2 projects with 75 MW are waiting to connect here (largest by capacity: battery storage). Contracted dates run from 26 Oct 2029 to 26 Oct 2029.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Elvanfoot (50MW) Energy Storage | ELVANFOOT ENERGY STORAGE 2 LIMITED | Battery storage | 50 | 26 Oct 2029 | Medium | 26 Oct 2029 | Scoping | 1 |
| Elvanfoot (25MW) Energy Storage | ELVANFOOT ENERGY STORAGE 3 LIMITED | Battery storage | 25 | 26 Oct 2029 | Medium | 26 Oct 2029 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Douglas West | SP Energy Networks | 19.0 km | 22 MW | 15 MW |
| Symington | SP Energy Networks | 19.0 km | 12 MW | 3.3 MW |
| Moffat | SP Energy Networks | 19.5 km | 8.5 MW | 3.6 MW |
Thinking of connecting near ELVANFOOT ENERGY STORAGE 132/33KV COLLECTOR SUBSTATION?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Elvanfoot substation: 44 MW waiting
- Elvanfoot 400/275/33kV: 10 MW waiting
- Rivox 132/33kV: 220 MW waiting
- Glenglass 132/33kV: 60 MW waiting
- Red Moss Farm 132kV: 300 MW waiting