Red Moss Farm 132kV: grid connection queue
Red Moss Farm 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 300 MW is waiting to connect here (largest by capacity: battery storage). Contracted dates run from 30 May 2031 to 30 May 2031.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| Red Moss Farm | QAIR RENEWABLES UK LIMITED | Battery storage | 300 | 30 May 2031 | Medium | 30 May 2031 | Scoping | 1 |
Dates that moved
Since 2 Jun 2026, connection dates here moved by a month or more 1 time: 1 later and 0 earlier. An earlier date can mean someone ahead dropped out or the queue was re-ordered.
| Week seen | Project | Was | Now | Change |
|---|---|---|---|---|
| 13 Oct 2026 | Red Moss Farm | 30 Oct 2030 | 30 May 2031 | +7 months |
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Douglas West | SP Energy Networks | 8.5 km | 22 MW | 15 MW |
| Symington | SP Energy Networks | 15.3 km | 12 MW | 3.3 MW |
| Lesmahagow | SP Energy Networks | 16.6 km | 10 MW | 15 MW |
| Corra Linn | SP Energy Networks | 16.8 km | 4.6 MW | 8 MW |
| Lanark | SP Energy Networks | 18.3 km | 26 MW | 17 MW |
| Fauldhead | SP Energy Networks | 19.5 km | 9.4 MW | 5.7 MW |
Thinking of connecting near Red Moss Farm 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- GLENTAGGART 150MW BESS 132kV SUBSTATION: 150 MW waiting
- Glentaggart WF 33kV: 42 MW waiting
- Redshaw 132kV Substation.: 620 MW waiting
- Redshaw 400kV: 504 MW waiting
- Bodinglee Wind Farm 132kV: 280 MW waiting