Redshaw 132kV Substation.: grid connection queue

Redshaw 132kV Substation. · SP Transmission (southern Scotland) · register of 26 November 2026

2 projects with 620 MW are waiting to connect here (largest by capacity: battery storage, mixed and other). Contracted dates run from 31 Oct 2036 to 31 Oct 2037.

2projects in the queue
620 MWwaiting to connect
0 MWalready connected
0 MWholding Gate 2
0date moves since 2 Jun 2026
0 MWat high date risk

What sits in the queue

Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).

ProjectCustomerTypeMWContracted dateDate riskLikely dateStageGate
Hagshaw LDESHAGSHAW LDES LTDBattery storage50031 Oct 2036Low31 Oct 2036Scopingnone
Clyde South Energy ParkRENEWCO POWER LIMITEDMixed and other12031 Oct 2037Low31 Oct 2037Scoping1

Dates that moved

No connection date here has moved by a month or more since 2 Jun 2026.

Local network capacity nearby

Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.

SubstationOperatorDistanceGeneration headroomDemand headroom
Douglas WestSP Energy Networks5.0 km22 MW15 MW
LesmahagowSP Energy Networks13.0 km10 MW15 MW
Corra LinnSP Energy Networks13.9 km4.6 MW8 MW
SymingtonSP Energy Networks15.1 km12 MW3.3 MW
LanarkSP Energy Networks15.6 km26 MW17 MW

Thinking of connecting near Redshaw 132kV Substation.?

Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.

Ask for a free check See a sample report

Paid screening reports from £1,950. Queue watch alerts you when anything here changes.