West Andershaw 132kV: grid connection queue
West Andershaw 132kV Substation · SP Transmission (southern Scotland) · register of 26 November 2026
1 project with 86 MW is waiting to connect here (largest by capacity: onshore wind). Contracted dates run from 30 Apr 2030 to 30 Apr 2030.
What sits in the queue
Sorted by contracted date. Register of 26 November 2026. Date risk and likely date come from how similar projects' dates actually moved over the last two years (how we work it out).
| Project | Customer | Type | MW | Contracted date | Date risk | Likely date | Stage | Gate |
|---|---|---|---|---|---|---|---|---|
| West Andershaw Wind Farm | WEST ANDERSHAW WIND FARM LIMITED | Onshore wind | 86 | 30 Apr 2030 | High | 16 Mar 2032 | Scoping | 1 |
Dates that moved
No connection date here has moved by a month or more since 2 Jun 2026.
Local network capacity nearby
Nearest distribution substations within 20 km, from each operator's published headroom data. Location is approximate. Check the operator's own map before relying on it.
| Substation | Operator | Distance | Generation headroom | Demand headroom |
|---|---|---|---|---|
| Douglas West | SP Energy Networks | 5.7 km | 22 MW | 15 MW |
| Lesmahagow | SP Energy Networks | 14.9 km | 10 MW | 15 MW |
| Fauldhead | SP Energy Networks | 16.6 km | 9.4 MW | 5.7 MW |
| Corra Linn | SP Energy Networks | 17.0 km | 4.6 MW | 8 MW |
| Cronberry | SP Energy Networks | 18.0 km | 7.9 MW | 7.3 MW |
| Symington | SP Energy Networks | 18.5 km | 12 MW | 3.3 MW |
Thinking of connecting near West Andershaw 132kV?
Tell us the site and size. We'll send you what sits ahead of it in the queue, free. It takes a day.
Ask for a free check See a sample reportPaid screening reports from £1,950. Queue watch alerts you when anything here changes.
Nearby connection points
- Bodinglee Wind Farm 132kV: 280 MW waiting
- Redshaw 132kV Substation.: 620 MW waiting
- Redshaw 400kV: 504 MW waiting
- GLENTAGGART 150MW BESS 132kV SUBSTATION: 150 MW waiting
- Glentaggart WF 33kV: 42 MW waiting